02.03.2013 Views

Downloadable - About University

Downloadable - About University

Downloadable - About University

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Multi-attribute utility 129<br />

lottery. After some thought, he indicates that this probability is 0.8, so<br />

k1 = 0.8. This suggests that the ‘swing’ from the worst to the best overrun<br />

time is seen by the project manager to be significant relative to project<br />

cost. If he hardly cared whether the overrun was 0 or 6 weeks, it would<br />

have taken only a small value of k1 to have made him indifferent to a<br />

gamble where overrun time might turn out to be at its worst level.<br />

To obtain k2, the weight for project cost, we offer the project manager<br />

a similar pair of options. However, in the certain outcome, project cost<br />

is now at its best level and the other attribute at its worst level. The<br />

probability of the best outcome in the lottery is now k2. These two options<br />

are shown in Figure 5.20.<br />

We now ask the project manager what value k2 would need to be to<br />

make him indifferent between the two options. He judges this probability<br />

to be 0.6, so k2 = 0.6. The fact that k2 is less than k1 suggests that the<br />

project manager sees the swing from the worst to the best cost as being<br />

less significant than the swing from the worst to the best overrun time.<br />

Having been offered a project which is certain to incur the lowest cost,<br />

he requires a smaller probability to tempt him to the lottery, where he<br />

might gain a project where overrun is also at its best level but where<br />

there is also a risk of a project with costs at their worst level.<br />

Finally, we need to find k3. This is a simple calculation and it can be<br />

shown that:<br />

k1 + k2 + k3 = 1, so k3 = 1 − k1 − k2<br />

Thus, in our case k3 = 1 − 0.8 − 0.6 =−0.4. The project manager’s multiattribute<br />

utility function is therefore:<br />

u(x1, x2) = 0.8 u(x1) + 0.6 u(x2) − 0.4 u(x1)u(x2)<br />

We can now use the multi-attribute utility function to determine the<br />

utilities of the different outcomes in the decision tree. For example, to<br />

find the utility of a project which overruns by 3 weeks and costs $60 000<br />

we proceed as follows. From the single-attribute functions we know that<br />

Figure 5.20<br />

Overrun Cost<br />

1.0<br />

Worst = 6 weeks Best: $50000<br />

k 2<br />

1 − k 2<br />

Overrun Costs<br />

Best = 0 weeks Best: $50000<br />

Worst = 6 weeks Worst: $140000

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!