VENTECH ENGINEERS, LLC.<br />
PROCEDURES<br />
1 OBJECTIVE<br />
<strong>ENGINEERING</strong> <strong>DRAWING</strong> <strong>CONTROL</strong><br />
1 OF 9<br />
4.5-6<br />
Effective Date: Jan. 6, 2011<br />
Revision: 2<br />
Approval: Kyle Ray<br />
The objective of this procedure is to define a standard method of controlling, numbering,<br />
issuing, revising and approving the engineering drawings generated by <strong>Ventech</strong><br />
Engineers, LLC.<br />
2 SCOPE<br />
This procedure applies to all engineering drawings generated for <strong>Ventech</strong> projects,<br />
studies, and proposals. For control of other project documentation and specifications<br />
generated by <strong>Ventech</strong> or outside of <strong>Ventech</strong>, see Procedure 4.5-2 "Project<br />
Documentation Control", and procedure 4.5-9 “Engineering Specification Control”.<br />
3 AUTHORITY<br />
Engineering Department managers are responsible for ensuring that the engineering<br />
drawing documentation is controlled in accordance with this procedure. The Piping<br />
Department Manager is responsible for maintaining this procedure.<br />
4 REFERENCES<br />
Procedure 4.5-2: Project Documentation Control<br />
Procedure 4.5-7: Magnetic Data Control<br />
Procedure 4.5-8: Proposal, Study and Project Number Assignment<br />
Work Instruction 4.4-PD-01: Work Instruction for Isometric Drafting<br />
5 PROCEDURES<br />
5.1 <strong>ENGINEERING</strong> <strong>DRAWING</strong> <strong>CONTROL</strong><br />
5.1.1 A drawing status report (See Example Form 4.5-6.1) shall be developed<br />
by each department manager at the beginning of each project. A drawing<br />
status report is not necessary for proposals and studies.<br />
5.1.2 The Project Secretary shall maintain the drawing status report for all<br />
engineering departments.
VENTECH ENGINEERS, LLC.<br />
PROCEDURES<br />
2 OF 9<br />
4.5-6<br />
Effective Date: Jan. 6, 2011<br />
Revision: 2<br />
Approval: Kyle Ray<br />
5.1.3 The person generating the drawing is responsible for inputting their name<br />
or initials along with the current date in the "BY" (drawn by) area in the<br />
title block. It is the responsibility of the department manager to ensure<br />
that the "start date" is recorded on the document and in the "Drawing<br />
Status Report".<br />
5.1.4 The drawing status report shall be issued to each department manager<br />
periodically as required by changes in drawing status. This will ensure<br />
that the reports are readily available to any employee needing to certify<br />
the status of a drawing.<br />
5.1.5 All magnetic copies of drawings shall be stored and archived in<br />
accordance with Procedure 4.5-7 "Magnetic Data Control".<br />
5.1.6 It is the responsibility of each department manager to maintain files<br />
containing hard copies of drawings. The original drawings shall be stored<br />
in a safe place to be readily retrieved for future copies. If necessary, a<br />
copy of the original can be placed in a stick file or other suitable location<br />
for reference to other disciplines. All drawings that have "hand" signatures<br />
in the proper blocks, as defined in this procedure, shall be the original.<br />
When an approved drawing is revised, the previously approved drawing<br />
shall have the word "VOID" stamped or written in ink on the original. The<br />
word "void" on these drawings shall ensure that only the current revision<br />
is in circulation. Approved drawings that have been voided, shall be kept<br />
for historical or possible legal reference. Each department shall have work<br />
instructions outlining how drawings are to be maintained within their<br />
department.<br />
5.1.7 The drawing status report will be issued periodically in accordance with<br />
the document matrix.<br />
5.2 <strong>ENGINEERING</strong> <strong>DRAWING</strong> NUMBERING ASSIGNMENT<br />
5.2.1 When a drawing is generated for a project, study or proposal a drawing<br />
number shall be assigned. Duplicate drawing numbers shall be<br />
dissimilated by the job number. If the drawing is a computer generated<br />
drawing, then the drawing number and the electronic file name are the<br />
same.
VENTECH ENGINEERS, LLC.<br />
PROCEDURES<br />
3 OF 9<br />
4.5-6<br />
Effective Date: Jan. 6, 2011<br />
Revision: 2<br />
Approval: Kyle Ray<br />
5.2.2 Each drawing shall contain at least the two blocks shown below. The<br />
standard <strong>Ventech</strong> border drawing has these blocks incorporated into the<br />
title block (See Attachment "A").<br />
Assigned Project Number,<br />
Study Number of<br />
Proposal Number<br />
JOB NUMBER<br />
XXXX-XX<br />
<strong>DRAWING</strong> NUMBER<br />
XXXX-XX<br />
Sequential Number<br />
Area Number<br />
Type of Drawing<br />
The X's in the preceding boxes shall be replaced in accordance with the<br />
following information. (Note: The X's will not appear on the actual<br />
drawing, they are for representation only.<br />
5.2.2.1 A project, study or proposal number should be assigned before<br />
a drawing is created. See Procedure 4.5-8 "Proposal, Study or<br />
Project Number Assignment." After an appropriate number has<br />
been assigned, the X's in the job number box shall be replaced<br />
with this number.<br />
5.2.2.2 Type of drawing shall be the first two X's in the drawing number<br />
box. They shall be selected from the list below.<br />
Civil/Structural Department<br />
AR - Architectural<br />
CR - Concrete<br />
CV - Civil<br />
SS - Structural Steel<br />
Electrical Department<br />
ED - Electrical Details<br />
EM - Electrical miscellaneous<br />
EO - Electrical One Lines<br />
EP - Electrical Plans<br />
ES - Electrical Schematics
VENTECH ENGINEERS, LLC.<br />
PROCEDURES<br />
4 OF 9<br />
4.5-6<br />
Effective Date: Jan. 6, 2011<br />
Revision: 2<br />
Approval: Kyle Ray<br />
Instrument Department<br />
ID - Instrument Drawings<br />
IL - Instrument Loops<br />
Mechanical Department<br />
MM - Mechanical Miscellaneous<br />
(Note: Equipment drawing numbers shall be in<br />
accordance with this Procedure, Section 5.2-3)<br />
Piping Department<br />
PA - Plot Plans and Equipment<br />
Arrangement<br />
PF - Process Flow Diagram<br />
PD - Piping & Instrument Diagram<br />
PK - Piping Key Plan<br />
PM - Piping Miscellaneous<br />
PP - Piping Plans and Sections<br />
(Note: Piping isometric drawing numbers shall be<br />
in accordance with 4.4-PD-01, Work Instruction for<br />
Isometric Drafting)<br />
5.2.2.3 The third X in the drawing number box will be separated from<br />
the first two letters with a hyphen. This X will represent the unit<br />
area number. (i.e., If unit area is 100, then this digit will be a<br />
1.) If there is only one area for the project, then area 100 shall<br />
be used.<br />
5.2.2.4 The fourth and fifth X's shall be the sequential number for a<br />
particular type of drawing. If a department exceeds 99<br />
drawings, then a sixth digit may be added.<br />
5.2.3 Equipment drawings shall not receive numbers as defined in 5.2.2. The<br />
equipment number shall be the drawing number. If the equipment<br />
requires more than one drawing, the sheet number shall dissimilate the<br />
drawing number. (i.e., if the equipment number is V-101 and requires<br />
three drawings, all three drawing numbers will be V-101 dissimilated by its<br />
respective sheet number.) If the drawing is a computer generated<br />
drawing, then the drawing number, along with the sheet number, will be
VENTECH ENGINEERS, LLC.<br />
PROCEDURES<br />
5 OF 9<br />
4.5-6<br />
Effective Date: Jan. 6, 2011<br />
Revision: 2<br />
Approval: Kyle Ray<br />
the electronic file name, (i.e., If the equipment number is V-101 and it is<br />
Sheet 2, then the electronic file number will be V101-2.<br />
5.3 <strong>ENGINEERING</strong> <strong>DRAWING</strong> ISSUANCE<br />
5.3.1 Prior to being issued, all drawings shall have the appropriate checked and<br />
approval blocks hand signed with ink in accordance with this Procedure,<br />
section 5.4. (Note: The ink used to sign drawings shall be a different color<br />
than black. This will dissimilate an original from a copy.)<br />
5.3.2 All drawings shall be distributed in accordance with the project document<br />
distribution matrix.<br />
5.3.3 All drawings issued in-house or to the client shall be issued using a<br />
transmittal form. (See Form 4.5-6.2)<br />
5.3.3.1 In-house transmittals of drawings shall be initiated by the<br />
Department Manager, squad leader or engineer.<br />
5.3.3.2 Transmittals to the client shall be initiated by the Project<br />
Manager.<br />
5.3.4 The Project Secretary shall assign a transmittal number to each<br />
transmittal. This number comes from the correspondence register, kept in<br />
the project files.<br />
5.3.4.1 The Project Secretary shall fill in the transmittal with the<br />
following information:<br />
Project Number<br />
Date<br />
Transmittal Number<br />
Page x of x<br />
Transmitted By = Initiator<br />
Item = Drawing Number<br />
Rev = Drawing Revision Number<br />
Description = Drawing Title Type of Transmittal<br />
(i.e., Preliminary/For Information, Approved for<br />
Construction, etc.)
VENTECH ENGINEERS, LLC.<br />
PROCEDURES<br />
6 OF 9<br />
4.5-6<br />
Effective Date: Jan. 6, 2011<br />
Revision: 2<br />
Approval: Kyle Ray<br />
Distribution = Document distribution matrix<br />
5.3.5 After the Project Secretary has completed the transmittal with the above<br />
information, the transmittal, along with the drawing(s), shall be returned to<br />
the initiator for approval.<br />
5.3.6 The initiator of an in-house transmittal shall review the transmittal for<br />
accuracy. When the initiator is satisfied with the information on the<br />
transmittal, that person shall sign or place initials by their name on the<br />
transmittal located in the "transmitted by" area. The initiator, if other than<br />
a department manager, shall turn the package over to the department<br />
manager for approval. If the department manager approves the<br />
transmittal, the department manager shall sign or initial the "approved by"<br />
area on the transmittal.<br />
5.3.6.1 After the in-house transmittal has been approved by the<br />
department manager, the transmittal and drawing(s) shall be<br />
returned to the Project Secretary. The Project Secretary shall<br />
forward the package to the Project Manager for final review.<br />
Once the Project Manager is satisfied with the package being<br />
transmitted, the Project Manager shall sign or initial the<br />
"approved by" area on the transmittal.<br />
5.3.7 The Project Manager shall review the transmittal to the client for<br />
accuracy. When the Project Manager is satisfied with the information on<br />
the transmittal, the Project Manager shall sign or place initials by their<br />
name in the "transmitted by" area.<br />
5.3.8 After the in-house or client transmittal has been finalized by the Project<br />
Manager, the package shall be returned to the Project Secretary. The<br />
Project Secretary shall reproduce and distribute transmittals and drawings<br />
per the transmittal.<br />
5.3.8.1 After drawings have been reproduced, the Project Secretary<br />
shall return originals to the initiator. The initiator shall place<br />
drawing(s) in their proper file.<br />
5.3.9 Any client request for drawings to be issued shall be made through the<br />
Project Manager. The Project Manager shall notify the department<br />
manager for any drawings that will be required.
VENTECH ENGINEERS, LLC.<br />
PROCEDURES<br />
5.4 <strong>ENGINEERING</strong> <strong>DRAWING</strong> REVISIONS AND APPROVALS<br />
7 OF 9<br />
4.5-6<br />
Effective Date: Jan. 6, 2011<br />
Revision: 2<br />
Approval: Kyle Ray<br />
5.4.1 IN GENERAL: The revision description area is located on the left side of<br />
the drawing title block (See Attachment "A"). It shall be used to record<br />
the type of revision that the drawing represents. A maximum of three<br />
revisions will be recorded on any given engineering drawing produced by<br />
<strong>Ventech</strong>. The person that is physically revising the drawing shall input<br />
their initials in the "By" block of the revision description area. They shall<br />
also input the type of revision along with the description. The "CHK"<br />
(checked by), "APP"(approved by) and "DATE" blocks shall be left blank<br />
for hand signatures and dates. Once the revision description area is filled<br />
with three revisions, the oldest revision shall be deleted and replaced with<br />
the new revision. If the preceding revision had hand signatures and/or<br />
dates in the "CHK" (checked by), "APP" (approved by) or "DATE" block,<br />
then these initials shall be electronically entered into their appropriate<br />
locations.<br />
5.4.2 The revision block is located on the lower right of the title block. (See<br />
Attachment "A"). It shall be used to record the current revision level of<br />
the drawing.<br />
5.4.3 PRELIMINARY ISSUES: Preliminary issues made during the<br />
development of a drawing shall bear the letter "A" in both the revision<br />
description area and the revision block. Subsequent revisions shall be<br />
dissimilated by using a numerical sequence, such as A1, A2, A3, etc.<br />
The revision description shall simply state the word "Preliminary".<br />
5.4.3.1 Preliminary drawings that are issued for reference do not need<br />
to be signed off in any of the checked by or the approval areas<br />
of the title block.<br />
5.4.4 CLIENT APPROVAL ISSUES: Drawings that are issued for client<br />
approval shall bear the letter "B" in both the revision description area and<br />
the revision block. Subsequent revisions shall be dissimilated by using a<br />
numerical sequence, such as B1, B2, B3, etc. The revision description<br />
shall simply state the words "Client Approval". At this time all preliminary<br />
revisions shall be deleted from the revision description area and only the<br />
client approval revisions shall be recorded henceforth.
VENTECH ENGINEERS, LLC.<br />
PROCEDURES<br />
8 OF 9<br />
4.5-6<br />
Effective Date: Jan. 6, 2011<br />
Revision: 2<br />
Approval: Kyle Ray<br />
5.4.4.1 Drawings that are being issued to the client shall have the<br />
"CHK" (checked by) and the "APP" (approved by) blocks in the<br />
revision description area hand signed. The "CHK" (checked by)<br />
block shall be hand signed by the person responsible for<br />
checking the drawing. The "APP" (approved by) block shall be<br />
hand signed by the department manager and the Project<br />
Manager. The "DATE" block next to the approval block shall<br />
have the date hand signed by the Project Manager.<br />
5.4.5 APPROVED FOR CONSTRUCTION ISSUES: Drawings that are issued<br />
approved for construction shall bear the number "0" (zero) in both the<br />
revision description area and the revision block. The revision description<br />
shall simply state the words "Approved For Construction". Subsequent<br />
revisions shall be dissimilated by using a numerical sequence, such as 1,<br />
2, 3, etc. The revision description shall briefly describe what was revised<br />
on the drawing.<br />
5.4.5.1 Drawings that are being issued for construction shall follow the<br />
same steps as defined in this Procedure, section 5.4.4.1. In<br />
addition to those steps, the checked and approval blocks next<br />
to the confidential statement are to be hand signed and dated<br />
(See Attachment "A"). These blocks are to be signed only if<br />
the drawing is at revision "0". Revision "0" indicates that the<br />
drawing is "Approved for Construction". The following<br />
personnel shall be responsible for signing and dating these<br />
blocks.<br />
"Drawn" block - Entered electronically by the<br />
person when the drawing was<br />
generated. (See section 5.1.3 of<br />
this Procedure)<br />
"Checked" block - The person responsible for<br />
checking the drawing.<br />
First "Approved" block - Department Manager<br />
Second "Approved" block - Project Engineer<br />
Third "Approved" block - Project Manager
VENTECH ENGINEERS, LLC.<br />
PROCEDURES<br />
6 DOCUMENT<br />
Document Location<br />
Transmittals Project Files<br />
Original Drawings Discipline Files<br />
Drawing Status Report Project Files<br />
9 OF 9<br />
4.5-6<br />
Effective Date: Jan. 6, 2011<br />
Revision: 2<br />
Approval: Kyle Ray