2.2 During detailed engineering after getting formal order, the approvals of the following are to be obtained from OIL<br />
(i) Control System cabinet Wiring Details<br />
(ii) Sensor locations<br />
(iii) Loop diagram & loop details<br />
(iv) Cable schedules<br />
(v) Project Implementation Schedule<br />
2.3 A Layout diagram of Gas Compressor Stations, details of Gas Compressors, line sizes etc will be provided to the<br />
successful bidder/supplier during installation & commissioning.<br />
3.0 All the Sensors for Online Gas Detection are to be installed in Hazardous area shall be certified by CIMFR/ERTL and<br />
approved by DGMS for operation in Zone 1, Zone 2, Gas group IIA & IIB (Division 1, Division 2, Gas group Class I,<br />
Group C&D) environment..<br />
3.1 Bidder shall confirm in their offer that they shall provide DGMS Approval before dispatching the items to OIL.<br />
3.2 The bidder shall provide written assurance that the DGMS approval is valid for at least 6 months at the time of dispatch of<br />
material. Dispatch clearance shall not be issued by OIL, if supplier cannot produce DGMS approval for their offered<br />
sensors with minimum 6 months validity during the time of inspection.<br />
4.0 Supplier needs to provide commissioning spares free of cost at the time of installation and commissioning as well as<br />
during test run of the system.<br />
4.1 Two sets (for each GCS) of Operation & Maintenance manual for Infrared (IR) On-Line Gas Monitoring System to be<br />
provided during commissioning of the system.<br />
4.2. Test certificates for each sensor have to be provided along with the supply.<br />
4.3 The materials shall be packed in robust cartoons so as to avoid damage in transit (shipment).<br />
4.0 OIL reserves the right to inspect, test and if necessary reject any part/parts after delivery at site (including incomplete<br />
manuals, catalogues, etc.) in case of any fault on the part of the supplier. It shall in no way be waived by the reason that<br />
the unit/item was previously inspected and passed by OIL as per Inspection Clause detailed elsewhere in the enquiry. To<br />
keep the unit fully operational, in case of failure of any item during the warranty period, it shall the suppliers responsibility<br />
to arrange replacement/repairing at site at their cost including customs, freight, etc. within a period of maximum 3(three)<br />
weeks from the date of notification of such failure. The warranty for the repaired item shall be correspondently extended<br />
by a period equal to that from the date of failure to the date of re-commissioning. In case of replacements, the warranty<br />
shall be for 1(one) year from the date of commissioning of the replaced item.<br />
6.0 Delivery being the essence of the tender, bidder should indicate their best delivery schedule (preferably within four (4)<br />
months from the date of placement of order/LC opening).<br />
7.0 Installation & Commissioning of Infrared (IR) On-Line Gas Monitoring System At GCS<br />
7.1 Installation and commissioning as well as testing of all the supplied Infrared (IR) On-Line Gas Monitoring System shall<br />
have to be carried out by the Supplier's competent personnel at OIL's suitable location in or around Duliajan, Assam<br />
(<strong>India</strong>) tentatively as under:<br />
i) GAS COMPRESSOR STATION- GCS-4<br />
ii) GAS COMPRESSOR STATION- GCS-JOYPUR<br />
iii) GAS COMPRESSOR STATION- GCS-USHAPUR<br />
iv) GAS COMPRESSOR STATION- GCS-KATHALGURI<br />
<strong>Tender</strong> No. SDG7299P13/09 Page 14 of 25