5. CONCLUSION<<strong>br</strong> />
Balance reserves of the deposit South<<strong>br</strong> />
Mining District Majdanpek were determined<<strong>br</strong> />
on the basis of limit natural indicators<<strong>br</strong> />
related to the quality of mineral resources<<strong>br</strong> />
and mining technical conditions of<<strong>br</strong> />
exploitation, using the software Whittle<<strong>br</strong> />
and Gemcom.<<strong>br</strong> />
For selection the most suitable contour<<strong>br</strong> />
of balance reserves, the deposit optimi<strong>za</strong>tion<<strong>br</strong> />
was made in the software Whittle,<<strong>br</strong> />
based on developed block model of deposit,<<strong>br</strong> />
where several variants were obtained<<strong>br</strong> />
in a contour of limit copper content 0.15%,<<strong>br</strong> />
more precisely 86 variants of open pits.<<strong>br</strong> />
The mentioned software package sets<<strong>br</strong> />
the open pit limit per Lersh-Grossman<<strong>br</strong> />
algorithm, and the Cut-off procedure was<<strong>br</strong> />
applied. This method is used to calculate a<<strong>br</strong> />
potential profit for each mineralized block<<strong>br</strong> />
and costs in the event of its excavation.<<strong>br</strong> />
Fig. 2. View of the final open pit contour<<strong>br</strong> />
Calculation of balance reserves was<<strong>br</strong> />
mode in the software Gemcom, module<<strong>br</strong> />
Volumetrics.<<strong>br</strong> />
Limit open pit for the aforementioned<<strong>br</strong> />
initial techno-economic parameters is the<<strong>br</strong> />
open pit with a factor of income equal to<<strong>br</strong> />
one, or the open pit No.36. Since the open<<strong>br</strong> />
pits from No.34 to No.38 are positive,<<strong>br</strong> />
according to the “best“ variant of excavation,<<strong>br</strong> />
with the existing data taken into optimi<strong>za</strong>tion,<<strong>br</strong> />
the open pit No.33 was selected<<strong>br</strong> />
for construction the open pit that<<strong>br</strong> />
includes the balance reserves. The assumed<<strong>br</strong> />
profit, obtained in the software<<strong>br</strong> />
package Whittle for the variant of open pit<<strong>br</strong> />
No.33, would provide the additional investments,<<strong>br</strong> />
while the economic value of<<strong>br</strong> />
deposit remains positive.<<strong>br</strong> />
No 4, <strong>2011</strong>. 91<<strong>br</strong> />
MINING ENGINEERING