Master Plan Summary - Aerodrom Ljubljana

Master Plan Summary - Aerodrom Ljubljana Master Plan Summary - Aerodrom Ljubljana

lju.airport.si
from lju.airport.si More from this publisher
22.02.2013 Views

Access Road • Relocation of access road within Phase 1. • Three new roundabouts to access the airport area (Design provided by the airport), • First roundabout = access to terminal (Terminal Link). • Second roundabout = access to commercial area (Commercial Link). • Third roundabout = access to cargo and GA area (Cargo Link). • Access road needs a second lane per direction in Phase 3. Terminal Link New Access Road Commercial Link Existing Access Road Cargo Link Terminal Curb • The total length of the new curb is 215 m and consists of; • Parking lane for taxis, drop-off and pick-up located directly in front of the terminal. • Maneuvering area in the back of the parking lane. • One-directional drive through lane. • Access road needs a second lane per direction in Phase 3. 40 41

Access Road<br />

• Relocation of access road within Phase 1.<br />

• Three new roundabouts to access the airport area (Design provided by the airport),<br />

• First roundabout = access to terminal (Terminal Link).<br />

• Second roundabout = access to commercial area (Commercial Link).<br />

• Third roundabout = access to cargo and GA area (Cargo Link).<br />

• Access road needs a second lane per direction in Phase 3.<br />

Terminal Link<br />

New Access Road<br />

Commercial Link<br />

Existing Access Road<br />

Cargo Link<br />

Terminal Curb<br />

• The total length of the new curb is 215 m and consists of;<br />

• Parking lane for taxis, drop-off and pick-up located directly in front of the terminal.<br />

• Maneuvering area in the back of the parking lane.<br />

• One-directional drive through lane.<br />

• Access road needs a second lane per direction in Phase 3.<br />

40 41