Condition requirement Means of monitoring during period under review Compliance achieved?<br />
3. Adverse effects in Kahouri<br />
Stream d/s of mixing zone<br />
Biological monitoring Yes<br />
4. Lapse period Not exercised N/A<br />
5. Optional review of consent Not exercised N/A<br />
N/A = not applicable<br />
Table 25 Summary of performance for Consent 5063-1 to discharge domestic septic tank effluent<br />
through a soakage field into or onto land<br />
Condition requirement Means of monitoring during period under review Compliance achieved?<br />
1. Septic tank & field soakage<br />
effluent treatment system be<br />
installed according to submitted<br />
plans<br />
2. No discharge shall enter a<br />
surface water body<br />
Inspections Yes<br />
Inspections Yes<br />
3. Optional review of consent Not exercised N/A<br />
N/A = not applicable<br />
During the year, the Company demonstrated a high level of environmental<br />
performance and compliance with the resource consents. During the year under<br />
review there were no incidents, and the site was well managed. Water quality<br />
monitoring indicated no adverse effects on biological communities as a result of the<br />
stormwater discharges to the Kahouri Stream or domestic effluent discharge (to land)<br />
from this site.<br />
7.6.4 Recommendations from the 2005-<strong>2006</strong> <strong>Annual</strong> Report<br />
In the 2005-<strong>2006</strong> <strong>Annual</strong> Report, it was recommended:<br />
1. THAT monitoring of discharges from Contact Energy Ltd <strong>Taranaki</strong> combined<br />
cycle power plant in the <strong>2006</strong>-<strong>2007</strong> year continue at the same level as in 2005-<br />
<strong>2006</strong>.<br />
This recommendation was implemented in the <strong>2006</strong>-<strong>2007</strong> monitoring year.<br />
7.6.5 Alterations to monitoring programmes for <strong>2007</strong>-2008<br />
In designing and implementing the monitoring programmes for air/water<br />
discharges in the region, the <strong>Taranaki</strong> <strong>Regional</strong> <strong>Council</strong> has taken into account the<br />
extent of information made available by previous authorities, its relevance under the<br />
Resource Management Act, the obligations of the Act in terms of monitoring<br />
emissions/discharges and effects, and subsequently <strong>report</strong>ing to the regional<br />
community, the scope of assessments required at the time of renewal of permits, and<br />
the need to maintain a sound understanding of industrial processes within <strong>Taranaki</strong><br />
emitting to the atmosphere/discharging to the environment.