3.4.2 Air<br />
46<br />
Air monitoring in the <strong>2006</strong>-<strong>2007</strong> monitoring period comprised of visual inspections.<br />
Deposition gauging is carried out on a biennial basis and was not conducted during<br />
the monitoring year under review. This is to be conducted in the <strong>2007</strong>-2008<br />
monitoring period.<br />
At the time of both inspections (14 December <strong>2006</strong> and 28 June <strong>2007</strong>) there were no<br />
off-site odours. Visible aerial emissions were observed during the June <strong>2007</strong><br />
inspection but did not cause odours offsite.<br />
3.5 Register of incidents<br />
The <strong>Taranaki</strong> <strong>Regional</strong> <strong>Council</strong> operates and maintains a register of all complaints or<br />
<strong>report</strong>ed and discovered excursions from acceptable limits and practices, including<br />
non-compliance with consents, which may damage the environment. The register<br />
(‘unauthorised incident register’) includes events where the company concerned has<br />
itself notified the <strong>Council</strong>. The register contains details of any investigation and<br />
corrective action taken.<br />
Incidents may be alleged to be associated with a particular site. If there is an issue of<br />
legal liability, the <strong>Council</strong> must be able to prove by investigation that the identified<br />
company is indeed the source of the incident, (or that the allegation cannot be<br />
proven).<br />
In the <strong>2006</strong>-<strong>2007</strong> year, there were no incidents recorded by the <strong>Council</strong> that were<br />
associated with <strong>Taranaki</strong> Galvanizers.<br />
3.6 Discussion<br />
3.6.1 Discussion of plant performance<br />
During the monitoring year under review, the performance of the <strong>Taranaki</strong><br />
Galvanizers site has been good.<br />
Fumes can be generated during the galvanising process on occasions. It is recognised<br />
that working conditions within the building may necessitate ventilation requiring<br />
that doors be kept open, and that the exhausting of fumes has not been demonstrated<br />
to lead to significant off-site environmental effects. The incident of fume generation<br />
has reduced since the plant was taken over by <strong>Taranaki</strong> Galvanizers.<br />
The stormwater catchment was generally kept clear of contaminants throughout the<br />
year, and wastewater was adequately bunded and managed well.<br />
3.6.2 Environmental effects of exercise of consents<br />
Stormwater discharges from the site were monitored during the year and effects on<br />
the unnamed tributary of the Kahouri Stream assessed. Water chemistry monitoring<br />
indicated that elevated zinc levels were continuing to occur in the stormwater (and<br />
leachate) discharge from the galvanising site, as a result of historical disposal of<br />
spent acid to a bore on the property. However, trends in zinc levels over time<br />
indicate that concentrations of zinc are continuing to drop, as the pH of the discharge