atw - International Journal for Nuclear Power | 04.2022
Ever since its first issue in 1956, the atw – International Journal for Nuclear Power has been a publisher of specialist articles, background reports, interviews and news about developments and trends from all important sectors of nuclear energy, nuclear technology and the energy industry. Internationally current and competent, the professional journal atw is a valuable source of information. www.nucmag.com
Ever since its first issue in 1956, the atw – International Journal for Nuclear Power has been a publisher of specialist articles, background reports, interviews and news about developments and trends from all important sectors of nuclear energy, nuclear technology and the energy industry. Internationally current and competent, the professional journal atw is a valuable source of information.
www.nucmag.com
Erfolgreiche ePaper selbst erstellen
Machen Sie aus Ihren PDF Publikationen ein blätterbares Flipbook mit unserer einzigartigen Google optimierten e-Paper Software.
atw Vol. 67 (2022) | Ausgabe 4 ı Juli
44
Emsland
REPORT
Operating sequence in 2021
100
90
80
70
60
50
40
30
20
Electrical output in %
100
80
60
40
20
10
0
0
January February March April May June July August September October November December
100
Apart from the 16.6 days refueling outage the Emsland nuclear
power
80
plant had been operating uninterrupted and mainly at full
load during the review period 2021. Producing a gross power
generation
60
of 11,356,583 MWh with a capacity factor of 95.37 %
the power plant achieved a very good operating result.
40
Planned 20 shutdowns
34 rd Refueling and 33 rd overall maintenance outage:
0
The annual outage was scheduled for the period 30 April to
17 May. The outage took 16.6 days from breaker to breaker.
In addition to the replacement of 52 fuel elements the following
major maintenance and inspection activities were
100
carried out:
80
• 60Inspection of core and reactor pressure vessel internals.
• Inspection of pressurizer valves.
40
• Inspection of a reactor coolant pumps.
• 20Pressure test on different coolers and tanks.
• Inspection on main condensate pump.
0
• Maintenance works on different transformers.
• Different automatic non-destructive examination.
Unplanned shutdowns and reactor/turbine trip
None.
Power reductions above 10 % and longer than for 24 h
26 March to 30 April: Stretch-out operation.
Delivery of fuel elements
In 2021 no fuel elements were delivered.
Waste management status
No CASTOR © cask loading was carried out during the review
period 2021.
At the end of the year 47 loaded casks were stored in the
local interim storage facility, operated by BGZ.
General points
In the year 2021, the surveillance audit of the quality
management system (ISO 9001:2015) and the recertification
of the environmental management system (ISO
14001:2015) were successfully carried out.
Positionierung:
Bezug, links, unten
X = 20,475 Y = 95,25 B = 173,5 H = 38,2
VGB: HKS6K 30 %
atw: 100 60 0 0
Report
Operating results 2021