16.08.2012 Aufrufe

Spezialtiefbau Magazin Special Foundation Magazine

Spezialtiefbau Magazin Special Foundation Magazine

Spezialtiefbau Magazin Special Foundation Magazine

MEHR ANZEIGEN
WENIGER ANZEIGEN

Sie wollen auch ein ePaper? Erhöhen Sie die Reichweite Ihrer Titel.

YUMPU macht aus Druck-PDFs automatisch weboptimierte ePaper, die Google liebt.

<strong>Spezialtiefbau</strong> <strong>Magazin</strong><br />

<strong>Special</strong> <strong>Foundation</strong> <strong>Magazin</strong>e<br />

foundation engineering


INHALTSVERZEICHNIS<br />

Vorwort der Geschäftsführung 3<br />

Parkgarage Reiterkogel - Hinterglemm, Salzburg 4<br />

Brenner Eisenbahn GmbH, Unterinntaltrasse, Baulos H4/3 6<br />

City-Tunnel Leipzig, Baulos B 8<br />

Spielberk Office Center, Brünn 10<br />

Neubau Stadtzentrum Eppendorf, Hamburg 12<br />

Fehrbelliner Höfe, Berlin 14<br />

Bürohochhaus „HOCH ZWEI“ und<br />

Bürogebäude „PLUS ZWEI“, Wien 16<br />

ÖBB Baulos Lainzer Tunnel LT 31 18<br />

Landungsbrücken St. Pauli Hochwasserschutz, Hamburg 20<br />

Tiergarten Schönbrunn, Wien, Renovierung Altes Palmenhaus 22<br />

Köln, U-Bahntrasse Nord-Süd, Haltestelle Severinstrasse 24<br />

Stahl Logistik Center, Lobau/Wien 26<br />

Zentrales Auslieferungslager HOFER in Ljubljana 28<br />

NÖ Landesgartenschau Tulln<br />

Rammpfahlarbeiten am Baumwipfelweg 30<br />

Kraftwerk Kühtai / Tirol 32<br />

City-Tunnel Leipzig, Vereisungsarbeiten 34<br />

B180 Reschenstraße Tirol, Errichtung von Seilsperren 36<br />

Standorte 38<br />

TABLE OF CONTENTS<br />

Foreword of the management 3<br />

Reiterkogel Parking Garage - Hinterglemm, Salzburg 5<br />

Brenner Eisenbahn GmbH, Unterinntal line, contract section H4/3 7<br />

Leipzig City Tunnel, section B 9<br />

Spielberk Office Center, Brno 11<br />

Construction of new city center in Eppendorf, Hamburg 13<br />

Fehrbelliner Höfe, Berlin 15<br />

„HOCH ZWEI“ High-Rise Office Building and<br />

„PLUS ZWEI“ Office Building, Vienna 17<br />

ÖBB LT 31 Baulos Lainz Tunnel contract section 19<br />

Flood control for St. Pauli landing bridges in Hamburg 21<br />

Schönbrunn Zoo, Vienna, Renovation of old Palm house 23<br />

Cologne, North/South subway line, Severinstrasse Station 25<br />

SLC steel logistics center, Lobau/Vienna 27<br />

Central HOFER distribution center in Ljubljana 29<br />

Lower Austrian State Garden Show in Tulln<br />

Driven pile construction at Baumwipfelweg 31<br />

Kühtai Power Plant / Tyrol 33<br />

Leipzig City Tunnel, Ground Freezing 35<br />

B180 Reschenstraße Tyrol, Rope barrier installation 37<br />

Locations 38<br />

2<br />

Titelbild: Bohrpfahlherstellung für die Donaubrücke in<br />

Traismauer, Niederösterreich<br />

Cover photo: Construction of bored piles at the Danube<br />

Bridge in Traismauer, Lower Austria<br />

In diesem <strong>Magazin</strong> stellen wir Sparten des<br />

<strong>Spezialtiefbau</strong>s vor und geben einen Einblick<br />

in unser umfangreiches Portfolio<br />

In this magazine we would like to present different<br />

sectors of special foundation and provide insight into<br />

our comprehensive service portfolio.<br />

Leistungsspektrum / Performance Spectrum<br />

Schlitzwände<br />

Dichtwände<br />

Schmalwände<br />

Baugrubenlösungen<br />

Bohrpfähle<br />

Großbohrungen<br />

Pfahlprüfungen<br />

Aufschlussbohrungen<br />

Kleinbohrpfähle<br />

Ankerungen<br />

Nagelwände<br />

Spritzbeton<br />

Rammpfähle<br />

Bodenverbesserungen<br />

Düsenstrahlverfahren<br />

(DSV/HDI)<br />

Injektionen<br />

Vereisung<br />

Vorspannarbeiten<br />

Hebetechnik<br />

Wasserhaltung<br />

Brunnenbau<br />

Felssicherung<br />

Diaphragm Walls<br />

Impervious Walls<br />

Cut Off Walls<br />

Construction Pits<br />

Bored Piles<br />

Large Diameter Drilling<br />

Pile tests<br />

Rotary Core Drilling<br />

Micropiles<br />

Ground Anchors<br />

Soil Nailing<br />

Shotcrete<br />

Driven Piles<br />

Soil Improvement<br />

Jet Grouting<br />

Grouting<br />

Ground Freezing<br />

Posttensioning<br />

Heavy Lifting Systems<br />

Dewatering<br />

Well Sinking<br />

Rock Stabilisation


Liebe Kundinnen, liebe Kunden!<br />

Mit der vorliegenden Zeitschrift soll erstmalig eine Zusammenstellung<br />

der <strong>Spezialtiefbau</strong>aktivitäten des ALPINE-Konzerns erfolgen.<br />

Das <strong>Spezialtiefbau</strong>-<strong>Magazin</strong> soll jährlich einmal erscheinen<br />

und sowohl an unsere externen Kunden, als auch an die Kunden<br />

aus dem Konzern adressiert werden.<br />

Fünf Unternehmen, verbunden mit einer gemeinsamen maschinentechnischen<br />

Abteilung und einem laufenden Wissenstransfer,<br />

bilden derzeit den <strong>Spezialtiefbau</strong>verband der ALPINE. Die Grund-<br />

Pfahl- und Sonderbau GmbH mit Sitz in Himberg, Kematen,<br />

Klagenfurt und Dornbirn, die Universale Grund- und Sonderbau<br />

mit Sitz in Berlin, Langenfeld, Hamburg, München und Leipzig,<br />

die Stump <strong>Spezialtiefbau</strong> GmbH mit Sitz in München, Berlin,<br />

Langenfeld, Chemnitz, Hannover und Colbitz, die Stump <strong>Spezialtiefbau</strong><br />

spol. s r.o. mit Sitz in Prag, Brünn und Ostrava und die<br />

Stump-Hydrobudowa Sp. z.o.o. mit Sitz in Warschau, Krakau<br />

und Posen bilden ein dichtes Netzwerk von Standorten in Österreich,<br />

Deutschland, Tschechien und Polen. Von diesen Bereichen<br />

aus werden auch Projekte im übrigen Osteuropa und Spanien<br />

abgewickelt. Geprägt durch konsequentes Wachstum sind wir<br />

mittlerweile zu einem der führenden europäischen <strong>Spezialtiefbau</strong>unternehmen<br />

aufgerückt.<br />

Wir planen und realisieren Projekte in allen Bereichen des<br />

Grundbaus. Dazu zählen Bohr-, Mikro- und Verdrängungspfähle,<br />

Ankerungen, Aufschlussbohrungen, Düsenstrahlverfahren,<br />

Niederdruckinjektionen und Bodenvernagelungen. Alle diese<br />

<strong>Spezialtiefbau</strong>gewerke sowie Felssicherungen und Sanierungen<br />

setzen wir auch im hochalpinen Gelände um. Ergänzt werden<br />

diese Tätigkeiten durch Vorspannarbeiten, Heben und Ziehen<br />

von schweren Lasten sowie die statische Sanierung von historischem<br />

Mauerwerk.<br />

Allen Kunden bieten wir durch unsere Stärke in den Einzelgewerken,<br />

kombiniert mit unserer Planungskompetenz, technisch<br />

und wirtschaftlich maßgeschneiderte Einzel- und Komplettlösungen,<br />

u.a. im gesamten Wohnungs- und Hochbau, im Verkehrswege-<br />

und Ingenieurbau sowie im Tunnel- und Kraftwerksbau.<br />

Durch gezielte Forschung und Entwicklung können wir<br />

auch schwierigste Herausforderungen annehmen.<br />

Wir wollen uns in den nächsten Jahren zum Innovationsführer im<br />

<strong>Spezialtiefbau</strong> entwickeln. Effizientes Arbeiten, gutes Arbeitsklima<br />

und die Sicherheit unserer Mitarbeiter bilden die Basis für<br />

den erfolgreichen Weg in die Zukunft.<br />

Unsere Kunden mit unserer Arbeit bestmöglich zufriedenzustellen<br />

ist uns ein ständiges Anliegen.<br />

Glück auf!<br />

Dear Customers,<br />

Dipl.-Ing. Dr. Peter Preindl<br />

For the first time, this magazine will present a summary of the<br />

ALPINE Group‘s special foundation activities. The <strong>Special</strong> <strong>Foundation</strong><br />

<strong>Magazin</strong>e will be published once a year and address both<br />

our external customers and the customers in our group.<br />

Five companies sharing one equipment and machinery department<br />

and an ongoing transfer of knowledge currently comprise<br />

ALPINE‘s special foundation associates. Grund- Pfahl- und<br />

Sonderbau GmbH with offices in Himberg, Kematen, Klagenfurt<br />

and Dornbirn, Universale Grund- und Sonderbau with offices<br />

in Berlin, Langenfeld, Hamburg, München and Leipzig, Stump<br />

<strong>Spezialtiefbau</strong> GmbH with offices in Munich, Berlin, Langenfeld,<br />

Chemnitz, Hannover and Colbitz, Stump <strong>Spezialtiefbau</strong><br />

spol. s r.o. with offices in Prague, Brno and Ostrava and Stump-<br />

Hydrobudowa Sp. z.o.o. with offices in Warsaw, Krakow and<br />

Posen provide a dense network of locations in Austria, Germany,<br />

the Czech Republic and Poland. Projects throughout Eastern<br />

Europe and Spain are also executed from these locations.<br />

Marked by steady growth, we meanwhile have become one of<br />

Europe‘s leading special foundation enterprises.<br />

We design and execute projects in virtually every field of geotechnical<br />

engineering, providing, e.g. bored piles, micropiles,<br />

driven piles, ground anchors, rotary core drilling, jet grouting,<br />

grouting and soil nailing. All of these special foundation activities<br />

as well as rock stabilisation and repairs are also provided in highalpine<br />

terrain. Our services are supplemented by posttensioning,<br />

lifting and pulling of heavy loads and the static rehabilitation of<br />

historic masonry.<br />

Our strength in the individual field of activity combined with our<br />

design competence allows us to offer our customers customtailored,<br />

technical and commercial, individual or full-service<br />

solutions in all kinds of residential and building construction,<br />

the construction of transport routes, civil engineering, tunnel<br />

construction, power plant construction, etc. Selective research<br />

and development allows us to accept even the most difficult<br />

challenges.<br />

We assume to become the leading special foundation innovators<br />

within the next few years. An efficient manner of working, a<br />

positive working atmosphere and job security for our staff create<br />

a strong basis for our future success.<br />

Our continuous goal is to provide the best possible service to our<br />

customers.<br />

Good luck!<br />

3


BAUGRUBENSICHERUNG<br />

PARKGARAGE REITERKOGEL - HINTERGLEMM, SALZBURG<br />

Auf Grund der prekären Parkplatzsituation im Tourismusort<br />

Hinterglemm wurde 2006 beschlossen, am Fuße der Skiliftstation<br />

Reiterkogel eine großzügige Parkgarage zu errichten. Die<br />

Herausforderung war, dass die Gesamtbauarbeiten nur von<br />

Ende Mai bis Ende November dauern durften. Die gigantischen<br />

Ausmaße der Garage stellten eine große Herausforderung dar.<br />

So hatte die Baugrube eine Tiefe von bis zu 27 m. Es wurden auf<br />

zwei Bauteilabschnitten Stellplätze für rund 360 PKW auf jeweils<br />

4 Parkdecks errichtet.<br />

Damit die zeitlichen und technischen Vorgaben erfüllt werden<br />

konnten, wählten die Spezialisten der GPS eine „kombinierte<br />

Verbaulösung“: verankerte Bohrpfahlwände kombiniert mit<br />

Unterfangungen und Hangsicherungen mittels Düsenstrahlverfahren<br />

und Nagelwänden. Unter Ausnutzung aller Zeitressourcen<br />

(Tag-/Nachtbetrieb und Wochenenden) wurde ein Terminplan<br />

erarbeitet, der eine zeitgerechte Fertigstellung garantierte.<br />

4<br />

Bauherr Bäder-Park GmbH, Saalbach-Hinterglemm<br />

Auftraggeber ARGE Parkgarage Reiterkogel<br />

Technische Geschäfsführung ALPINE Niederlassung Salzburg<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• 3.300 m Bohrpfahl d 90 cm<br />

• 15.000 m vorgespannte Anker System VSL<br />

• 600 m DSV Säulen d 130 cm<br />

• 200 m 2 Spritzbetonwand<br />

Ausführung <strong>Spezialtiefbau</strong> GPS Grund- Pfahl- und Sonderbau GmbH, Filiale Kärnten<br />

Kontakt office@gps-bau.com<br />

Auftragssumme <strong>Spezialtiefbau</strong> 2,2 Mio. EUR<br />

Bauzeit <strong>Spezialtiefbau</strong>arbeiten: 12 Wochen<br />

Komplette Tiefgarage: 22. Mai bis 30. November 2007<br />

Das Gesamtprojekt wurde von der ARGE Parkgarage Reiterkogel<br />

unter der technischen Geschäftsführung der ALPINE Nieder-<br />

lassung Salzburg fristgerecht fertiggestellt.<br />

Die fertige Baugrube wurde nach nur 12 Wochen Bauzeit von der<br />

GPS übergeben. Am 30. November wurde die Parkgarage von<br />

den ersten Skitouristen benutzt.


REITERKOGEL PARKING GARAGE - HINTERGLEMM, SALZBURG<br />

In 2006 it was decided to build a spacious parking garage at the<br />

foot of the Reiterkogel ski lift station to alleviate the precarious<br />

parking situation in the Hinterglemm tourist resort. The challenge<br />

was to finish the construction from the end of May to the end<br />

of November. The garage‘s gigantic proportions posed a big<br />

challenge, e.g. the construction pit had a depth of up to 27 m.<br />

Parking spaces for approx. 360 cars were provided on 4 park<br />

decks in two stages of construction.<br />

To be able to meet the deadline and technical prerequisites, the<br />

specialists at GPS selected a „combined solution“: anchored<br />

bored piles combined with an jet grouting and soil nailing underpinning<br />

solution.<br />

A time schedule was set up, taking advantage of all available<br />

time resources (day/night operations and weekends) to guarantee<br />

that construction would be completed on time.<br />

Client Bäder-Park GmbH, Saalbach-Hinterglemm<br />

The following special foundation services were provided:<br />

• 3,300 m bored piles d 90 cm<br />

• 15,000 m prestressed strand anchors sytem VSL<br />

• 600 m jet grouting columns d 130 cm<br />

• 200 m 2 soil nailing wall<br />

The project was completed on time by the Reiterkogel Parking<br />

Garage JV, managed by ALPINE‘s Salzburg branch.<br />

The completed construction pit was handed over by GPS after<br />

just 12 weeks of construction.<br />

The first ski tourists used the parking garage on November 30.<br />

Principal ARGE Parkgarage Reiterkogel, Technical management: ALPINE‘s Salzburg Branch<br />

Technical Management ALPINE Salzburg Branch<br />

<strong>Special</strong> foundation contractor GPS Grund- Pfahl- und Sonderbau GmbH, Carinthia Branch<br />

Contact office@gps-bau.com<br />

Construction period <strong>Special</strong> foundation construction: 12 weeks<br />

Entire parking garage: May 22 - November 30, 2007<br />

Contract value EUR 2.2 million<br />

CONSTRUCTION PITS<br />

5


BAUGRUBENSICHERUNG<br />

BRENNER EISENBAHN GMBH, UNTERINNTALTRASSE,<br />

BAULOS H4/3<br />

Im Hauptbaulos H4/3 errichtet die GPS für die BEG Brenner<br />

Eisenbahn GmbH einen wesentlichen Teilabschnitt der neuen<br />

Eisenbahntrasse im Unterinntal. Insgesamt sind auf einer Länge<br />

von 2,6 km Tunnel in offener und bergmännischer Sonderbauweise<br />

zu errichten. Die besondere Herausforderung für die GPS<br />

stellen die Baugruben mit Tiefen bis zu 15 m dar, denn ab ca.<br />

1,5 m trifft man bereits auf das Grundwasser. Die GPS ist hierbei<br />

sowohl für die Planung der Baugruben der offenen Bauweise als<br />

auch für die Ausführung der erforderlichen <strong>Spezialtiefbau</strong>maßnahmen<br />

verantwortlich.<br />

Wesentlich für eine erfolgreiche Abwicklung war die Adaption<br />

notwendiger Bohr- und Injektionsmethoden an die Gegebenheiten<br />

vor Ort. So wurden temporäre Litzenanker mit Gebrauchslasten<br />

bis zu 1300 kN eingebaut.<br />

Die tiefliegende DSV - Sohle wurde in Zusammenarbeit mit den<br />

6<br />

Bauherr BEG Brenner Eisenbahn GmbH<br />

Auftraggeber ARGE H4/3 ALPINE/GPS<br />

Technische Geschäftsführung: ALPINE Zweigniederlassung Tirol<br />

Ausführung <strong>Spezialtiefbau</strong> GPS Grund- Pfahl- und Sonderbau GmbH<br />

Kontakt office@gps-bau.com<br />

Bauzeit <strong>Spezialtiefbau</strong>arbeiten 2006 bis 2009<br />

Auftragssumme <strong>Spezialtiefbau</strong> 25,9 Mio. EUR<br />

Schwesterfirmen Stump <strong>Spezialtiefbau</strong> und der GSB Grund- und<br />

Sonderbau Berlin hergestellt.<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• 7.500 m Bohrpfähle d 90 cm und d 120 cm<br />

• 38.000 m vorgespannte Litzenanker System VSL<br />

• 36.000 m Auftriebsanker, Stabanker d 57,5mm<br />

• 1.300 m² Schlitzwand d 80 cm<br />

• 12.500 m² tiefliegende DSV-Sohle<br />

• 4.000 m² vernagelte Spritzbetonwände<br />

• 600 t Stahl-Vergurtungsarbeiten<br />

• 14 Monate Wasserhaltungs- und Brunnenarbeiten<br />

• 2.000 m Aufschlussbohrung mit d bis 319 mm<br />

• Planung der Baugrubensicherung der offenen Bauweise


BRENNER EISENBAHN GMBH, UNTERINNTAL LINE,<br />

CONTRACT SECTION H4/3<br />

GPS is currently executingg the main H4/3 section of the new<br />

railroad line in the Unterinntal for BEG Brenner Eisenbahn GmbH.<br />

Tunnels are to be constructed over a total length of 2.6 km by<br />

the cut & cover and drill & blast methods. The construction pits<br />

with depths down to 15 m pose a special challenge for GPS since<br />

groundwater is already encountered at a depth of approx.<br />

1.5 meters. GPS is in charge of designing the construction pits by<br />

the cut and cover method and for providing the necessary special<br />

foundation services. For the successful execution of the project,<br />

it was necessary to adapt the required drilling and injection<br />

methods to the local conditions, e.g. the installation of temporary<br />

strand anchors with service loads of up to 1,300 kN.<br />

The jet grouted slab was placed in collaboration with the<br />

company‘s subsidiaries, Stump <strong>Spezialtiefbau</strong> and GSB Grund-<br />

und Sonderbau, Berlin.<br />

Client BEG Brenner Eisenbahn GmbH<br />

Principal H4/3 ALPINE/GPS JV<br />

Technical management: ALPINE, Tyrol Branch, GPS<br />

<strong>Special</strong> foundation contractor GPS Grund- Pfahl- und Sonderbau GmbH<br />

Contact office@gps-bau.com<br />

Construction period <strong>Special</strong> foundation construction: 2006 to 2009<br />

Contract value EUR 25.9 million<br />

CONSTRUCTION PIT<br />

The following special foundation services were provided:<br />

• 7,500 m bored piles, d 90 cm and d 120 cm<br />

• 38,000 m prestressed strand anchors, system VSL<br />

• 36,000 m uplift rod anchors, 57.5 mm<br />

• 1,300 m² diaphragm wall, d 80 cm<br />

• 12,500 m² jet grouted slab<br />

• 4,000 m² soil nailing wall<br />

• 600 t steel trussing<br />

• 14 months of dewatering and well sinking<br />

• 2,000 m rotary core drilling with d up to 319 mm<br />

• Design of the open cut construction pits<br />

7


BAUGRUBENSICHERUNG<br />

CITy-TUNNEL LEIPZIG, BAULOS B<br />

Der City-Tunnel Leipzig ist der letzte und zentrale Baustein in der<br />

Neuordnung des Eisenbahnsystems im Großraum Leipzig. Mit<br />

seiner Inbetriebnahme wird das S-Bahn-System grundlegend neu<br />

geordnet und die Anbindung der Region an die Stadt verbessert.<br />

Der Tunnel wird das Zentrum der Messestadt vom Bayerischen<br />

Bahnhof bis zum Hauptbahnhof unterqueren. Den Hauptabschnitt<br />

(Gesamtlänge von 2,4 km) bildet das Baulos B mit der<br />

Errichtung von 4 unterirdischen Stationen im Zentrum der Stadt.<br />

Die Universale Grund- und Sonderbau GmbH Berlin war für<br />

die Ausführung der Schlitzwand und HDI-Arbeiten mit einem<br />

Gesamtvolumen von 32 Mio. Euro verantwortlich. Zusätzlich<br />

wurden Dichtblöcke mit einem Auftragsvolumen von ca.<br />

EUR 3,0 Mio. ausgeführt.<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• Schlitzwandarbeiten<br />

39.000 m² d 1.000 mm bzw. 1.500 mm<br />

8<br />

Bauherr DB Energie GmbH, DB Netz AG, DB Station & Service AG, vertreten durch den Freistaat<br />

Sachsen, endvertreten durch DEGES<br />

(Deutsche Einheit Fernstraßenplanungs- und – bau GmbH)<br />

Auftragnehmer ARGE City-Tunnel Leipzig Los B<br />

Partner der Arbeitsgemeinschaft Dywidag Bau GmbH, ALPINE Deutschland AG Niederlassung Untertagebau,<br />

Oevermann Vermögensverwaltungs GmbH & Co.KG, Universale Grund- und<br />

Sonderbau Gesellschaft m.b.H. Zweigniederlassung Berlin, STRABAG AG<br />

Ausführung <strong>Spezialtiefbau</strong> Universale Grund- und Sonderbau GmbH, Berlin<br />

Kontakt gsb.berlin@gps-bau.com<br />

Bauzeit 2005 bis 2007<br />

Auftragssumme ca. 35,0 Mio. EUR<br />

• HDI –Arbeiten<br />

25.000 m³ Sohleaussteifung<br />

3.000 m³ Dichtsohle<br />

6.000 m³ Dichtblöcke<br />

• Ankerungsarbeiten<br />

31.000 m vorgespannte Litzenanker 600 kN bis 1000 kN<br />

Zur Abdeckung von Leistungsspitzen wurden die Schlitzwandarbeiten<br />

in Zusammenarbeit mit den Spezialisten der GPS, Grund-<br />

Pfahl- und Sonderbau GmbH aus Österreich ausgeführt. Die<br />

HDI-Arbeiten erfolgten in Kooperation mit Stump <strong>Spezialtiefbau</strong><br />

GmbH, Niederlassung Berlin. Mit dieser Bündelung der personellen<br />

und technischen Ressourcen des Spezialtiefverbundes<br />

der ALPINE-Gruppe war es möglich, alle Arbeiten termingerecht<br />

durchzuführen.


LEIPZIG CITy TUNNEL, SECTION B<br />

The Leipzig City Tunnel is the last and most important link in the<br />

reorganisation of the railroad system in the greater Leipzig area.<br />

Upon commissioning, it will fundamentally reorganise the entire<br />

rapid transit system and improve the region‘s connections to the<br />

city. The tunnel will lead below the city center from the Bavarian<br />

Train Station to the Central Train Station. Contract section B is<br />

the main section (with a total length of 2.4 km) and will involve<br />

the construction of 4 underground stations in the city center.<br />

Universale Grund- und Sonderbau GmbH in Berlin was responsible<br />

for providing the diaphragm walls and the jet grouting for an<br />

overall amount of EUR 32 million. In addition, impervious blocks<br />

were installed for an amount of approx. EUR 3 million.<br />

The following special foundation services were provided:<br />

• Diaphragm walls:<br />

39,000 m² d 1,000 mm and 1,500 mm<br />

Client DB Energie GmbH, DB Netz AG, DB Station & Service AG, represented by the<br />

State of Saxony, in turn represented by DEGES<br />

(Deutsche Einheit Fernstrassenplanungs- und – bau GmbH).<br />

Contractor City Tunnel Leipzig JV, section B<br />

Joint venture partners Dywidag Bau GmbH, ALPINE Deutschland AG (Underground Construction Branch),<br />

Oevermann Vermögensverwaltungs GmbH & Co.KG, Universale Grund- und<br />

Sonderbau Gesellschaft m.b.H. (Berlin Branch), STRABAG AG<br />

<strong>Special</strong> foundation contractor Universale Grund- und Sonderbau GmbH, Berlin<br />

Contact gsb.berlin@gps-bau.com<br />

Construction period 2005 to 2007<br />

Contract value approx. EUR 35 million<br />

CONSTRUCTION PITS<br />

• Jet grouting:<br />

25,000 m³ bracings<br />

3,000 m³ sole foundation slabs<br />

6,000 m³ impervious blocks<br />

• Single-phase slurry walls: 16,000 m 3 d 1,000 mm to<br />

1,500 mm, depths to 30 m<br />

• Ground Anchors: 31,000 m prestressed strand anchors<br />

600 kN to 1000 kN<br />

During peak periods diaphragm walls were installed together<br />

with the specialists at GPS, Grund- Pfahl und Sonderbau GmbH<br />

from Austria. The jet grouting was provided in collaboration<br />

with Stump <strong>Spezialtiefbau</strong> GmbH, Berlin branch. Pooling the<br />

human and technical resources available from the ALPINE<br />

Group‘s special foundation construction network made it possible<br />

to complete the work on time.<br />

9<br />

6


BAUGRUBENSICHERUNG<br />

SPIELBERK OFFICE CENTER, BRüNN<br />

Am Südrand der Stadt, im Schwemmland des Flusses Svartka,<br />

begann im Jahr 2005 der Bau eines modernen Verwaltungszentrums.<br />

In einem ersten Schritt wurden fünf Bürovillen errichtet,<br />

die bereits in Betrieb sind. Im März 2007 startete der Bau zweier<br />

multifunktionaler Hochbauten, den „TOWERS“.<br />

Als höchst problematisch für die unterirdische Konstruktion<br />

erwies sich die geologische Beschaffenheit des Geländes, verwässerte<br />

Schotter- und Sandböden, Neogen-Lehmböden, lehmige<br />

Sandböden und wieder verwässerte Sandböden bis in eine Tiefe<br />

von 80 m. Die Realisierung der Tiefbauarbeiten und die Verankerung<br />

der Schlitzwände mit einer Tiefe von 17 m, erfolgte durch<br />

die STUMP <strong>Spezialtiefbau</strong> GmbH, Bohrpfahlarbeiten und den Verbau<br />

der Baugrube realisierte GEOSPOL Brno spol.s r.o., technisch<br />

unterstützt von der GPS Wien.<br />

10<br />

Bauherr CTP Invest spol.s r.o. , CTPark Humpolec 1571, 396 01 Humpolec<br />

Ausführung <strong>Spezialtiefbau</strong> STUMP <strong>Spezialtiefbau</strong> spol.s r.o.<br />

GEOSPOL Brno spol.s r.o.<br />

GPS Grund- Pfahl- und Sonderbau GmbH, Wien<br />

Kontakt geospol@geospol-brno.cz<br />

Bauzeit März bis Oktober 2007<br />

Auftragssumme <strong>Spezialtiefbau</strong> 2,40 Mio. EUR<br />

Die Sicherung der Baugrube wurde mit einer 800 mm dicken<br />

Schlitzwand nach einer Entwicklung der Firma Fundos GmbH<br />

gewährleistet. Für die Stabilität sorgten 145 temporäre Litzenanker.<br />

Für die Pfahlbohrung kamen Schneckenortbetonpfähle zur<br />

Anwendung.<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• Tiefe der Schlitzwände 15-17,5 m<br />

• Fläche der Schlitzwände 4.560 m 2<br />

• Ankerlänge 19-21 m<br />

• Gesamtausmaß der Anker 2.904 m<br />

• Pfähle mit d 900 mm 3.476 m<br />

• Pfähle mit d 600 mm 280 m


SPIELBERK OFFICE CENTER, BRNO<br />

Construction of a modern administration center started in 2005<br />

on the southern edge of the city, in the bottomland of the Svartka<br />

River. The five office villas completed during the first stage of<br />

construction are already in use. Construction of the „TOWERS,“<br />

two multipurpose high rise buildings, started in March 2007.<br />

The geological condition of the ground proved to be extremely<br />

problematical for the underground structure: diluted gravel and<br />

sandy soils, neogen clay soils, loamy sandy soils and a further<br />

layer of diluted sandy soils down to a depth of 80 m. The special<br />

foundation construction and anchorage for the diaphragm walls<br />

down to a depth of 17 m were provided by STUMP <strong>Spezialtiefbau</strong><br />

GmbH. The bored piles and construction pit were provided by<br />

GEOSPOL Brno spol.s r.o. with the technical assistance of GPS<br />

Vienna.<br />

The construction pit was retained by a diaphragm wall with a<br />

thickness of 800 mm designed by Fundos GmbH. Its stability<br />

was guaranteed by 145 temporary strand anchors. CFA-piles<br />

(continous flight auger piles) were used for the pile foundation.<br />

The following special foundation services were provided:<br />

• Depth of diaphragm wall 15-17.5 m<br />

• Area of diaphragm wall 4,560 m 2<br />

• Anchor length 19-21 m<br />

• Total anchor dimension 2,904 m<br />

• Piles with d 900 mm 3,476 m<br />

• Piles with d 600 mm 280 m<br />

Principal CTP Invest spol.s r.o., CTPark Humpolec 1571, 396 01 Humpolec<br />

<strong>Special</strong> foundation contractor STUMP <strong>Spezialtiefbau</strong> spol.s r.o.<br />

GEOSPOL Brno spol.s r.o.<br />

GPS Grund- Pfahl- und Sonderbau GmbH, Vienna<br />

Contact geospol@geospol-brno.cz<br />

Construction period March to October 2007<br />

Contract value EUR 2.4 million<br />

CONSTRUCTION PITS<br />

11


GEWERK BAUGRUBENSICHERUNG<br />

NEUBAU STADTZENTRUM EPPENDORF,<br />

HAMBURG<br />

Im Hamburger Stadtteil Eppendorf wird durch den Umbau eines<br />

ehemaligen Einkaufszentrums ein neues Stadtteilzentrum errichtet.<br />

Das Projekt umfasst die Errichtung einer Tiefgarage, neue<br />

Einzelhandelsgeschäfte und den Bau eines siebengeschossigen<br />

Bürogebäudes.<br />

Dafür errichtete die Universale Grund- und Sonderbau GmbH im<br />

Zeitraum von Juli bis Dezember 2007 die komplette Baugrube<br />

mit Hilfe einer verankerten Ortbetonschlitzwand. Wegen der<br />

Grundwasserverhältnisse war es erforderlich, eine Auftriebssicherung<br />

herzustellen. Insgesamt 184 Stk. Auftriebspfähle mit<br />

Längen bis zu 12 m wurden gebohrt und versetzt. Gegen das<br />

zustrebende Wasser wurde ein komplettes Wasserhaltungskonzept<br />

erarbeitet.<br />

12<br />

Bauherr Hamburger Immobilien Projekt Gesellschaft<br />

Mittelweg 100, 20149 Hamburg<br />

Ausführung <strong>Spezialtiefbau</strong> Universale Grund- und Sonderbau GmbH Berlin<br />

Kontakt gsb.berlin@gps-bau.com<br />

Bauzeit Juli bis Dezember 2007<br />

Auftragssumme 3,1 Mio. EUR<br />

Der Arge Partner, ALPINE Bau Deutschland AG, wird in enger<br />

Zusammenarbeit mit dem <strong>Spezialtiefbau</strong> bis Herbst 2008 das<br />

schlüsselfertige Gebäude errichten.<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• 6.700 m² Ortbetonschlitzwand 600 mm und 800 mm<br />

• 6.750 m vorgespannte Anker 3-5 litzig<br />

• 41.000 m³ Erdaushub<br />

• 184 Stk. Auftriebspfähle d 62,5 mm, L=12,0 m<br />

• Wasserhaltung


CONSTRUCTION OF NEW CITy CENTER IN EPPENDORF,<br />

HAMBURG<br />

A former shopping center is being converted into a new city center<br />

in the Hamburg district of Eppendorf. The project involves the<br />

construction of an underground garage, new retail stores and a<br />

seven-storey office building.<br />

Universale Grund- und Sonderbau GmbH provided the entire<br />

construction pit between July and December 2007 with an<br />

anchored diaphragm wall. The groundwater conditions made it<br />

necessary to provide uplift control. A total of 184 uplift piles with<br />

lengths of up to 12 m were drilled and installed. A comprehensive<br />

drainage system was designed to prevent water inflow.<br />

Client / Principal Hamburger Immobilien Projekt Gesellschaft<br />

Mittelweg 100, 20149 Hamburg, Germany<br />

<strong>Special</strong> foundation contractor Universale Grund- und Sonderbau GmbH, Berlin<br />

Contact gsb.berlin@gps-bau.com<br />

Construction period July to December 2007<br />

Contract value EUR 3.1 million<br />

CONSTRUCTION PITS<br />

The joint venture partner, ALPINE Bau Deutschland AG, will complete<br />

the turnkey building together with the special foundation<br />

construction by the fall of 2008.<br />

The following special foundation services were provided:<br />

• 6,700 m² diaphragm wall, 600 mm and 800 mm<br />

• 6,750 m prestressed strand anchors, 3 to 5 strands<br />

• 41,000 m³ excavation<br />

• 84 pcs. uplift piles, d 62.5 mm, L=12 m<br />

• Dewatering<br />

13


BAUGRUBENSICHERUNG<br />

FEHRBELLINER HÖFE, BERLIN<br />

Das Bauprojekt „Fehrbelliner Höfe“ liegt in Berlin-Mitte und<br />

umfasst ein Gebäudeensemble klassischer Altbauten aus der<br />

Gründerzeit und ehemaliger Fabrikgebäude. Die Gesamtfläche<br />

beträgt ca. 7.300 m². Der Bauherr, die ORCO Immobilien GmbH,<br />

ein führender Investor und Projektentwickler im Bereich Gewerbe-<br />

und Wohnimmobilien, nahm an diesem Bestandsobjekt<br />

umfassende Baumaßnahmen vor. Die Altbauten wurden saniert<br />

und neue Bauten einschließlich einer Tiefgarage mit ca. 200<br />

Stellplätzen errichtet. Es entstanden exklusive Wohneinheiten mit<br />

Loftcharakter und Penthousewohnungen.<br />

Die Arbeitsgemeinschaft, Grund- und Sonderbau GmbH (GSB)<br />

und Gebr. Kemner GmbH, erstellte die Baugrube und plante<br />

die Ausführung für eine 3-geschossige Tiefgarage inmitten<br />

der Altbebauung. Zur Errichtung der Baugrube wurden technisch<br />

äußerst anspruchsvolle Unterfangungsarbeiten mittels<br />

Düsenstrahlverfahren (HDI) vorgenommen. Von außen wurde<br />

mit Großgeräten und von innen in den Kellern mit Kleinstgeräten<br />

unter engsten räumlichen Bedingungen gearbeitet. Die<br />

Unterfangungen dienen als Sicherung und Ertüchtigung der<br />

14<br />

Bauherr Orco Immobilien GmbH, Berlin<br />

Bestandsbauwerke und der Grenzbebauung, sowie als Baugrubenumschließung<br />

für die zu erstellende Tiefgarage. Die verbleibenden<br />

Baugrubenwandbereiche bestehen aus aufgelösten<br />

Bohrpfahlwänden, deren Felder mit Spritzbeton ausgefacht sind.<br />

Die Baugrube wurde rückwärtig mit Verpressankern in 2 bis 4<br />

Lagen gesichert und anschließend bis zu 16 m Tiefe ausgehoben.<br />

Die HDI-Unterfangungskörper wurden fast ausschließlich im<br />

Geschiebemergel fester Konsistenz hergestellt.<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• HDI - außen: ca. 2.800 m³ statische HDI-Kubatur,<br />

Düskörperlängen bis zu 20 m<br />

• HDI - innen: ca. 2.000 m³ statische HDI-Kubatur,<br />

Düskörperlängen bis zu 17 m<br />

• 70 Bohrpfähle d 620 mm und 750 mm mit Längen<br />

bis zu 20 m<br />

• 270 vorgespannte Litzenanker mit Gesamtlänge<br />

von 4.000 m<br />

• Spritzbetonausfachung ca. 900 m²<br />

• Bodenaushub ca. 40.000 m³<br />

Auftraggeber ARGE Grund- und Sonderbau GmbH und Gebr. Kemner GmbH<br />

Ausführung <strong>Spezialtiefbau</strong> Universale Grund- und Sonderbau GmbH, Berlin<br />

Kontakt gsb.berlin@gps-bau.com<br />

Bauzeit April 2007 bis April 2008<br />

Auftragssumme <strong>Spezialtiefbau</strong> ca. 3,0 Mio. EUR


FEHRBELLINER HÖFE, BERLIN<br />

The „Fehrbelliner Höfe“ construction project is located in the<br />

center of Berlin and encompasses a building ensemble of classic<br />

old buildings dating from the period of rapid industrial expansion<br />

at the end of the 19th century as well as former factory<br />

buildings. It has a total area of approx. 7,300 m². The client,<br />

ORCO Immobilien GmbH, a leading investor and project developer<br />

for industrial and residential properties, undertook extensive<br />

constructional measures to improve these buildings. The old<br />

buildings were rehabilitated and new buildings including a<br />

200-car underground garage constructed. They now accommodate<br />

exclusive residential units in the loft style as well as<br />

penthouse apartments.<br />

A joint venture consisting of Grund- und Sonderbau GmbH<br />

(GSB) and Gebr. Kemner GmbH provided the construction pit<br />

and designed the 3-storey underground garage in the center<br />

of the existing development. Technically sophisticated underpinning<br />

was installed in the construction pit by means of jet<br />

grouting. Whereas heavy equipment was used on the outside,<br />

the inside required light equipment in extremely tight condi-<br />

Client Orco Immobilien GmbH, Berlin<br />

tions. The underpinning is used to stabilise and strengthen the<br />

existing buildings and provides a construction pit enclosure for<br />

the underground garage to be built. The remaining construction<br />

pit walls consist of a combined bored pile - shotcrete solution.<br />

The construction pit was stabilised with 2 - 4 layers of grouted<br />

anchors and excavated to a depth of up to 16 m. Most of the jet<br />

grouting was executed in solid clay.<br />

The following special foundation services were provided:<br />

• Exterior jet grouting: approx. 2.800 m³ lengths of up to 20 m<br />

• Interior jet grouting: approx. 2.000 m³ lengths of up to 17 m<br />

• 70 bored piles d 620 mm und 750 mm with lengths of<br />

up to 20 m<br />

• 270 prestressed strand anchors with a total length of<br />

4,000 m<br />

• Shotcrete infill approx. 900 m²<br />

• Soil excavation approx. 40,000 m³<br />

Principal ARGE Grund- und Sonderbau GmbH and Gebr. Kemner GmbH<br />

<strong>Special</strong> foundation contractor Universale Grund- und Sonderbau GmbH, Berlin<br />

Contact gsb.berlin@gps-bau.com<br />

Construction period April 2007 to April 2008<br />

Contract value approx. EUR 3 million<br />

CONSTRUCTION PITS<br />

15


BAUGRUBENSICHERUNG<br />

BüROHOCHHAUS „HOCH ZWEI“ UND<br />

BüROGEBäUDE „PLUS ZWEI“, WIEN<br />

Auf einem rund 40.000 m² großen Grundstück Vorgartenstraße/Ecke<br />

Trabrennstraße im zweiten Wiener Gemeindebezirk<br />

entsteht das VIERTEL ZWEI. In diesem neuen Stadtteil werden<br />

attraktive Büros, ein Hotel, Restaurants und kleine Shops, eingebettet<br />

in ein durchgängiges Grünraumkonzept mit eigenem See,<br />

geschaffen.<br />

Für das Bürohochhaus HOCH ZWEI und das Bürogebäude<br />

PLUS ZWEI wurde von der GPS eine bis zu 12 m tiefe Baugrube<br />

errichtet. Da die Aushubsohle ca. 9 m unter Grundwasserspiegel<br />

lag, wurde eine wasserdichte Umschließung mit Hilfe einer<br />

Betonschlitzwand hergestellt. Die Ableitung der Horizontallasten<br />

erfolgte über vorgespannte Temporäranker. Diese wurden nach<br />

16<br />

Bauherr U2 Stadtentwicklung GmbH<br />

Auftraggeber Universale Bau GmbH, Wien<br />

Ausführung <strong>Spezialtiefbau</strong> GPS Grund- Pfahl- und Sonderbau GmbH, Wien<br />

Kontakt office@gps-bau.com<br />

Bauzeit Februar bis Dezember 2007<br />

Auftragssumme <strong>Spezialtiefbau</strong> 3,05 Mio. EUR<br />

Abschluss der Arbeiten wieder vollkommen ausgebaut. Für die<br />

Grundwasserabsenkung wurden 9 Stk. Vertikalfilterbrunnen mit<br />

Tiefen bis zu 27 m abgeteuft.<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• 6.500 m 2 Schlitzwand d 80 cm und 100 cm<br />

• 175 Stk. Vorgespannte Litzenanker, vollkommen wieder<br />

ausbaubar nach der GPS Schockmethode<br />

• Wasserhaltung<br />

• 9 Stk. Vertikalfilterbrunnen, Tiefe bis 27 m,<br />

Pumprate bis 80 l/sek.<br />

• 360 Stk. Schneckenortbetonpfähle d 65 cm und 55 cm


„HOCH ZWEI“ HIGH-RISE OFFICE BUILDING AND<br />

„PLUS ZWEI“ OFFICE BUILDING, VIENNA<br />

VIERTEL ZWEI is being built on a piece of property measuring<br />

approx. 40,000 m² at Vorgartenstrasse/corner of Trabrennstrasse<br />

in Vienna‘s second district. Attractive offices, a hotel, restaurants<br />

and small shops will emerge in this new district, embedded in a<br />

rolling landscape with a private lake.<br />

GPS provided a construction pit of up to 12 m in depth for the<br />

HOCH ZWEI high-rise office building and the PLUS ZWEI office<br />

building. Since the bottom of the pit is approx. 9 m below<br />

groundwater level, a waterproof enclosure was provided by<br />

means of concrete diaphragm wall. Horizontal loads were transfered<br />

into the ground by prestressed temporary anchors that<br />

were removed upon completion.<br />

Client U2 Stadtentwicklung GmbH<br />

Principal Universale Bau GmbH, Vienna<br />

<strong>Special</strong> foundation contractor GPS Grund- Pfahl- und Sonderbau GmbH, Vienna<br />

Contact office@gps-bau.com<br />

Construction period February to December 2007<br />

Contract value EUR 3,05 million<br />

CONSTRUCTION PITS<br />

9 vertical filter wells were drilled to depths of up to 27 m to<br />

lower the groundwater level.<br />

The following special foundation services were provided:<br />

• 6,500 m 2 diaphragm wall d 80 cm and 100 cm<br />

• 175 pcs. prestressed strand anchors, completely removable<br />

by means of the GPS shock method<br />

• Dewatering<br />

• 9 pcs. vertical filter wells down to a depth of 27 m,<br />

pumping rate up to 80 l/sec.<br />

• 360 pcs. CFA-piles d 65 cm and 55 cm<br />

17


ANKERUNGEN<br />

ÖBB BAULOS LAINZER TUNNEL LT 31<br />

Das Bauvorhaben der Österreichischen Bundesbahnen (ÖBB-Infrastruktur<br />

Bau AG) der „Lainzer Tunnel“ ist eines der zentralen<br />

Infrastruktur-Projekte im Großraum Wien. Die neue 12,8 km<br />

lange Verbindungsstrecke zwischen West-, Süd- und Donauländebahn<br />

wird für eine wesentliche Entlastung der Wiener<br />

Hauptverkehrswege sorgen.<br />

Im Baulos LT31 – Maxing wurden zwei Tunnelröhren durch innerstädtisches<br />

Bebauungsgebiet geführt. Auf Grund der äußerst<br />

komplexen Geologie mussten als setzungsmindernde Maßnahmen<br />

Ortsbrustanker aus GFK-Material eingesetzt werden.<br />

Erschwert wurden die Bohrarbeiten durch die extrem enge<br />

Zufahrt im Mittelteil des Ulmenstollens. Insgesamt stand als Aufstandsfläche<br />

für das Bohrgerät eine maximale Breite von 2,80 m<br />

zur Verfügung. Für diese Arbeiten adaptierte und montierte die<br />

GPS eine spezielle Bohrlafette.<br />

18<br />

Bauherr ÖBB - Infrastruktur Bau Aktiengesellschaft<br />

Auftraggeber ARGE Lainzer Tunnel LT 31<br />

Ausführung <strong>Spezialtiefbau</strong> GPS Grund- Pfahl- und Sonderbau GmbH<br />

Kontakt office@gps-bau.com<br />

Bauzeit April bis Dezember 2007<br />

Auftragssumme <strong>Spezialtiefbau</strong> 1,25 Mio. EUR<br />

Zusätzlich waren unter diesen beengten Verhältnissen 10 Kernbohrungen<br />

in eine Tiefe von bis zu 35 m notwendig.<br />

Am selben Baulos wurde von der Oberfläche aus, ein DSV-Dichtschott<br />

mit einer Tiefe von ca. 25 m gebaut, um Wasser- und<br />

Sandeintritte in die aufzufahrenden Tunnelabschnitte zu minimieren.<br />

Auf Grund des anstehenden Bodens, feinkörnige Sande<br />

und Tone, und der zum Teil großen Neigung der Säulen (bis zu<br />

30° Neigung) kam abermals ein adaptiertes Bohrgerät von der<br />

firmeneigenen MTA zum Einsatz.<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• Ortsbrustanker aus GFK-Material 1.980 m<br />

• DSV Dichtschott 3.070 m Säulen d 1,50 m<br />

• Kernbohrungen 10 Stk d 146 mm


ÖBB LT 31 BAULOS LAINZ TUNNEL CONTRACT SECTION<br />

The „Lainz Tunnel“ project commissioned by the Austrian<br />

Federal Railway (ÖBB-Infrastruktur Bau AG) is one of the largest<br />

infrastructure projects in the greater Vienna area. The new<br />

12.8 km junction line between the Western, Southern and<br />

Donaulände Railroads will provide significant relief for the major<br />

traffic routes in Vienna.<br />

Two tunnel tubes were installed through the urban development<br />

area in the LT31–Maxing contract section. Face anchors made of<br />

GFR material had to be installed due to the extremely complex<br />

geological conditions. Drilling operations were further complicated<br />

by the extremely narrow access road to the center of the<br />

sidewall tunnel. At the widest point, only 2.80 m were available<br />

to set up the drilling equipment. GPS adapted and mounted a<br />

special drill truck for these operations.<br />

It was also necessary to execute 10 core drillings at depths down<br />

Client ÖBB - Infrastruktur Bau Aktiengesellschaft<br />

Principal LT 31 Lainzer Tunnel JV<br />

<strong>Special</strong> foundation contractor GPS Grund- Pfahl- und Sonderbau GmbH<br />

Contact office@gps-bau.com<br />

Construction period April to December 2007<br />

Contract value EUR 1,25 million<br />

GROUND ANCHORS<br />

to 35 m under these tight conditions.<br />

A jet-grouted impervious wall with a depth of approx. 25 m was<br />

installed from the surface in the same contract section to prevent<br />

water and sand from penetrating into the tunnel sections to be<br />

excavated. Due to the in-situ soil, fine-grained sands and clays,<br />

and the steep inclination of the columns (some as much as 30°),<br />

another adapted drill provided by the company‘s mechanical<br />

engineering division was used.<br />

The following special foundation services were provided:<br />

• Face anchors made of GFR material 1,980 m<br />

• Jet-grouted impervious walls 3,070 m<br />

columns d 1.50 m<br />

• Rotary drilling 10 pcs. d 146mm<br />

19


KLEINBOHRPFAHL<br />

LANDUNGSBRüCKEN ST. PAULI HOCHWASSERSCHUTZ,<br />

HAMBURG<br />

Im Zuge des Hochwasserschutzprogramms in Hamburg wird<br />

der Hochwasserschutz an den St. Pauli Landungsbrücken<br />

erneuert. Hierbei wird vor die vorhandene Spundwand, eine<br />

neue kombinierte Spundwand gesetzt, die mit insgesamt 64<br />

Verpresspfählen rückverankert werden soll. Für die gesamte<br />

Baustelleneinrichtung auf Pontons (Bohr- und Materialponton)<br />

stehen max. 25 m zwischen der vorhandenen Kaimauer und der<br />

vorgelagerten Pontonanlage zur Verfügung.<br />

Eine spezielle Herausforderung ist der Verpresspfahleinbau unter<br />

dem Einfluss der Gezeiten. In einem Rhythmus von ca.<br />

6 Stunden wechseln sich Hoch- und Niedrigwasser ab. Durch<br />

das immer wiederkehrende Ein- und Ausströmen des Wassers<br />

ergeben sich Gezeitenströme, die besondere Aufmerksamkeit<br />

bei der Verpresspfahlherstellung erfordern. Der Höhenunterschied<br />

zwischen dem mittleren Tidehochwasser und dem mittleren<br />

Tideniedrigwasser beträgt ca. 3,60 m. Bei den 47°<br />

20<br />

geneigten, mehrfach gekoppelten Verpresspfählen in den Brückenbereichen<br />

bleibt ein kleines Zeitfenster für den Einbau, da<br />

nur bei Niedrigwasser gebohrt werden kann.<br />

Eingebaut wurden in der ersten Bauphase (September bis<br />

Oktober 2007) 64 Stück doppelt korrosionsgeschützte Kleinbohrpfähle<br />

d 63,5 mm in Längen zwischen 17 und 31 m. Nach<br />

der Einbringung der kombinierten Spundwand (Januar bis Mai<br />

2008) müssen alle Verpresspfähle auf endgültige Längen von<br />

20 bis 35 m verlängert werden.<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• 64 Stk. Kleinbohrpfähle d 63,5 mm in Längen<br />

zwischen 17 und 31 m<br />

Bauherr Freie und Hansestadt Hamburg, Behörde für Stadtentwicklung und Umwelt,<br />

Amt für Bau und Betrieb, Abt. Hochwasserschutz<br />

Auftraggeber HOCHTIEF Construction AG, Niederlassung CEM, Hamburg<br />

Ausführung <strong>Spezialtiefbau</strong> Stump <strong>Spezialtiefbau</strong> GmbH, Niederlassung Hannover<br />

Kontakt hannover@stump.de<br />

Bauzeit September 2007 bis Mai 2008<br />

Auftragssumme <strong>Spezialtiefbau</strong> 1,0 Mio. EUR


FLOOD CONTROL FOR ST. PAULI LANDING BRIDGES IN<br />

HAMBURG<br />

The St. Pauli landing bridges were rehabilitated as part of<br />

Hamburg‘s flood control program. A new, combined sheet pile<br />

wall with a total of 64 grouted piles was installed as rear anchoring<br />

behind the existing sheet pile wall. Only a maximum of<br />

25 m were available between the existing wharf and the pontoons<br />

set up to accommodate the site equipment (drilling and<br />

material pontoons).<br />

The installation of the grouted piles presented a special challenge<br />

because of the tides. High and low tides alternated every<br />

6 hours. The continuous ebb and flow of the water resulted in<br />

tidal currents that required special attention for the installation<br />

of the grouted piles. The difference in height between the average<br />

high and low tide was approx. 3.6 m. Only a small period<br />

of time was available to install the grouted piles at an inclination<br />

of 47° since it was only possible to drill at low tide.<br />

MICROPILING<br />

64 double corrosion protected micro-piles, d 63.5 mm in<br />

lengths ranging between 17 and 31 m were placed during the<br />

first stage of construction (September to October 2007).<br />

Upon completion of the sheet pile wall (January to May 2008)<br />

all of the micro piles had to be extended to final lengths ranging<br />

between 20 and 35 m.<br />

The following special foundation services were provided:<br />

• 64 pcs. micro piles d 63.5 mm, lengths ranging between<br />

17 and 31 m<br />

Client Free Hanseatic city of Hamburg, Dept. for Urban Development and the Environmental<br />

Affairs, Office for Construction and Operation, Flood Control Division<br />

Principal HOCHTIEF Construction AG, Business Unit CEM, Hamburg<br />

<strong>Special</strong> foundation contractor Stump <strong>Spezialtiefbau</strong> GmbH, Hannover Branch<br />

Contact hannover@stump.de<br />

Construction period September 2007 to May 2008<br />

Contract value EUR 1 million<br />

21


DüSENSTRAHL-VERFAHREN (DSV/HDI)<br />

TIERGARTEN SCHÖNBRUNN, WIEN<br />

RENOVIERUNG ALTES PALMENHAUS<br />

In den Sommermonaten 2007 wurde ein weiterer Schritt zur<br />

Sanierung des Tiergartens in Schönbrunn getan. Das alte Palmenhaus<br />

wurde renoviert.<br />

Voraussetzung für eine dauerhafte Sanierung ist eine Verbesserung<br />

der Fundamente. Die Spezialisten der Grund- Pfahl- und<br />

Sonderbau (GPS) wählten eine Fundamentsertüchtigung im<br />

bewährten Düsenstrahlverfahren.<br />

Wie bei derartigen Baumaßnahmen oft notwendig, wurden die<br />

Arbeiten im Inneren und im äußeren des Gebäudes vorgenommen.<br />

Insgesamt wurden in der äußerst kurz bemessenen Bauzeit<br />

von nur einem Monat ca. 265 m³ DSV-Körper hergestellt.<br />

22<br />

Bauherr Schönbrunner Tiergarten Ges.m.b.H.<br />

Auftraggeber Bmst. Dipl.-Ing. Franz Mörtinger & Co. GmbH<br />

Ausführung <strong>Spezialtiefbau</strong> GPS Grund- Pfahl- und Sonderbau GmbH, Himberg<br />

Kontakt office@gps-bau.com<br />

Bauzeit Juli bis August 2007<br />

Auftragssumme <strong>Spezialtiefbau</strong> 0,2 Mio. EUR<br />

Zusätzlich wurde ein kurzer Abschnitt mit Hilfe eines Injektionsbohranker<br />

IBO R32/15 gebohrt, verpresst und verankert.<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• DSV-Säulen im Außenbereich 365 m³<br />

• Injektionsbohranker 100 m IBO R32/20<br />

• Kernbohrungen 20 m d 150 mm


SCHÖNBRUNN ZOO, VIENNA<br />

RENOVATION OF OLD PALM HOUSE<br />

Another step towards the rehabilitation of Schönbrunn Zoo was<br />

taken during the 2007 summer months. The old Palm House<br />

was renovated.<br />

An improvement of the foundation was required for a long-lasting<br />

rehabilitation. The specialists at Grund- Pfahl- und Sonderbau<br />

(GPS) chose to strengthen the foundation by means of the<br />

effective jet grouting process.<br />

As often required for constructional measures of this type, the<br />

work was carried out on the inside and outside of the building.<br />

Approx. 265 m³ of jet grouted bodies were installed in the extremely<br />

short construction period of just one month.<br />

Client Schönbrunner Tiergarten Ges.m.b.H.<br />

Principal Bmst. Dipl.-Ing. Franz Mörtinger & Co. GmbH<br />

<strong>Special</strong> foundation contractor GPS Grund- Pfahl- und Sonderbau GmbH, Himberg<br />

Contact office@gps-bau.com<br />

Construction period July to August 2007<br />

Contract value EUR 0.2 million<br />

JET-GROUTING<br />

A short section was also drilled, grouted and anchored with IBO<br />

R32/15 injection anchors.<br />

The following special foundation services were provided:<br />

• Jet grouted columns on the outside 365 m³<br />

• Injection anchors 100 m IBO R32/20<br />

• Rotary drilling 20 m d 150 mm<br />

23


NIEDERDRUCKINJEKTIONEN / VEREISUNG<br />

KÖLN, U-BAHNTRASSE NORD-SüD,<br />

HALTESTELLE SEVERINSTRASSE<br />

Die Nord-Süd Stadtbahn Köln ist das derzeit größte städtebauliche<br />

Projekt Deutschlands und zählt zugleich zu den größten<br />

archäologischen Ausgrabungsstätten in einer europäischen<br />

Metropole.<br />

Das Haltestellenbauwerk Severinstraße wird im Wesentlichen<br />

unterirdisch erstellt. Beide Röhren werden über eine Länge von<br />

circa 60 Metern mit einer Innenschale versehen und seitlich<br />

geöffnet, so dass über diesem Bereich ein offener Querschnitt<br />

entsteht. Zwischen den Tunnelröhren sind an der Nord- und<br />

Südseite des Bahnsteiges jeweils Treppenaufgänge und Aufzüge<br />

vorgesehen. Diese Bahnsteigzugänge werden in offener Bauweise<br />

im Schutz von Schlitzwänden und Bohrpfählen hergestellt.<br />

Als Vorausmaßnahme zur eigentlichen Herstellung war eine<br />

umfangreiche Bodenverbesserungsmaßnahme mit Hilfe von Niederdruckinjektionen<br />

im Manschettenrohrverfahren notwendig.<br />

Der Injektionskörper diente zur Stabilisierung des anstehenden<br />

Bodens zwischen den beiden Tunnelröhren. Erst nach gelungener<br />

Verfestigung war es möglich, die unterirdisch gelegene<br />

Haltestelle herzustellen.<br />

Sämtliche Arbeiten wurden aus einem Vorstollen mit einem<br />

Durchmesser von 2,50 m durchgeführt.<br />

24<br />

Bauherr Kölner Verkehrs-Betriebe AG<br />

Auftraggeber ARGE Nord-Süd Stadtbahn Köln, Los Süd<br />

Die Abdichtung dieses Vorstollens gegen einströmendes Grundwasser<br />

erfolgte mittels vorweg versetzten Vereisungslanzen.<br />

Auf Grund der beengten Verhältnisse kamen für die Bohrarbeiten<br />

zwei Bohrgeräte der Type Hütte 202 mit aufgesetzter<br />

Rotationslafette zum Einsatz. Diese erlaubten ein schnelles und<br />

wirtschaftliches Abbohren der Manschettenrohre in jede beliebige<br />

Richtung.<br />

Insgesamt wurden 4.700 m Manschettenrohre an 583 Bohrstellen<br />

versetzt. Über 1.330 Manschettenventile wurden anschließend<br />

ca. 6.000 m³ Bodenvolumen injiziert und verfestigt.<br />

Zwölf Injektionspumpen waren dafür rund im die Uhr im Einsatz.<br />

Nachfolgend wurden weitere 1.500 m Bohrung hergestellt und<br />

148 Vereisungslanzen eingebaut.<br />

Die Baustelle konnte termingerecht in sechs Monaten technisch<br />

einwandfrei abgewickelt werden.<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• Bodeninjektionskörper 6.000 m 3<br />

• Versetzung von Manschettenrohren 4.700 m<br />

• Vereisungslanzen 148 Stk<br />

Ausführung <strong>Spezialtiefbau</strong> STUMP <strong>Spezialtiefbau</strong> GmbH, Niederlassung Langenfeld<br />

Kontakt info@stump.de<br />

Bauzeit März bis Oktober 2007<br />

Auftragssumme <strong>Spezialtiefbau</strong> 1,25 Mio. EUR


COLOGNE, NORTH/SOUTH SUBWAy LINE,<br />

SEVERINSTRASSE STATION<br />

Cologne‘s North/South urban railway is currently Germany‘s<br />

largest urban development project and one of the biggest<br />

archeological excavation sites in a European city.<br />

The Severinstrasse station will essentially be built underground.<br />

Both tubes will have an inner shell over a length of approx.<br />

60 meters that is open on the sides, creating an open crosssection<br />

in this sector. Staircases and elevators are to be installed<br />

between the tunnel tubes on the northern and southern ends<br />

of the platform. The platforms will be executed by the open cut<br />

method using diaphragm walls and bored piles.<br />

Extensive soil improvement using grouting was required prior to<br />

construction of the station. The injection body served to stabilize<br />

the in-situ soil between the two tunnel tubes. The underground<br />

part of the station was built after the soil stabilization process<br />

was completed.<br />

The work was performed through a foretunnel with a diameter<br />

of 2.5 m.<br />

Client Kölner Verkehrs-Betriebe AG<br />

GROUTING / FREEZING<br />

The previous tunnel was sealed against the inflow of groundwater<br />

by means of previously installed freezing lances.<br />

Due to the extreme lack of space, two „Hütte“ 202 drill rigs with<br />

a modified drill truck were used. These made it possible to drill<br />

the sleeved pipes quickly and economically in any direction.<br />

A total of 4,700 m of sleeved pipes were placed at 583 drilling<br />

sites. Approx. 6,000 m³ of soil were subsequently grouted and<br />

set in place through 1,330 sleeve valves, requiring twelve injection<br />

pumps to be employed around the clock.<br />

Subsequently an additional 1,500 m were drilled and 148 freezing<br />

lances installed.<br />

The project was completed on time by the six-month deadline.<br />

The following special foundation services were provided<br />

• Grouted body 6,000 m 3<br />

• Installation of sleeved pipes 4,700 m<br />

• Freezing lances 148 pcs<br />

Principal Cologne North/South Urban Railway JV, southern section<br />

<strong>Special</strong> foundation contractor STUMP <strong>Spezialtiefbau</strong> GmbH, Langenfeld Branch<br />

Contact info@stump.de<br />

Construction period March to October 2007<br />

Contract value EUR 1.25 million<br />

25


RAMMPFäHLE<br />

STAHL LOGISTIK CENTER, LOBAU/WIEN<br />

Im Wiener Ölhafen Lobau wird von der SLC Stahl Logistik Center<br />

GmbH ein neues Stahlverarbeitungswerk errichtet. Die Standortwahl<br />

traf man unter Bedachtnahme der Erreichbarkeit des<br />

Werkes sowohl per Schiff als auch per Bahn.<br />

Da in diesem Bereich, bedingt durch Bombardements des<br />

Ölhafens während des zweiten Weltkrieges und der anschließenden<br />

Nutzung als Ölumschlagplatz, eine Kontaminierung des<br />

Untergrundes nicht ausgeschlossen werden konnte, wäre bei<br />

der ursprünglich vorgesehenen Gründung mittels Bohrpfählen<br />

die fachgerechte Entsorgung des anfallende Bodenmaterials mit<br />

hohen Kosten verbunden gewesen. Daher wurde von den Spezialisten<br />

der Grund- Pfahl- und Sonderbau (GPS) eine Variante mit<br />

Rammpfählen ausgearbeitet.<br />

Als Tieffundierung des dreischiffigen Werks, bestehend aus<br />

Produktions-, Öl- und Blechlagerhalle, wurden insgesamt 205<br />

Stück Ortbetonrammpfähle, System Zeissl-GPS, hergestellt. Diese<br />

dienen zur Abtragung der Gebäudelasten. Da bei drei Pfahlgruppen<br />

in unmittelbarer Nähe eine OMV Mitteldruckgasleitung im<br />

Untergrund verläuft, wurden bei der Herstellung dieser Pfähle<br />

Erschütterungsmessungen an der Leitung durchgeführt. Die<br />

durch die Pfahlherstellung verursachten Schwingungen zeigten<br />

dabei keine negativen Auswirkungen.<br />

Die Nutzlasten der Bodenplatte werden über insgesamt 898<br />

Stück mantelverpresste HLV®-Pfähle 118 mm in den Untergrund<br />

abgetragen. Diese übernehmen auch die Auftriebssicherung des<br />

Werkes. Im Bereich der aus rückverankerten Spundbohlen<br />

26<br />

Bauherr SLC Stahl Logistik Center GmbH, Wien<br />

Auftraggeber HABAU GmbH<br />

Ausführung <strong>Spezialtiefbau</strong> GPS Grund- Pfahl- und Sonderbau GmbH, Himberg<br />

Kontakt office@gps-bau.com<br />

Bauzeit Oktober 2007 bis April 2008<br />

Auftragssumme <strong>Spezialtiefbau</strong> 0,94 Mio. EUR<br />

bestehenden Hafenbeckenmauer werden die Bauwerkslasten<br />

von mantelverpressten HLV®-Pfählen 170 mm aufgenommen.<br />

Diese müssen exakt zwischen den bestehenden Rückverankerungen<br />

versetzt werden. Dies stellt kein Problem für das verwendete<br />

HLV®-Pfahl System dar.<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• 205 Stück Ortbetonrammpfahl System Zeissl-GPS mit einer<br />

Last bis 1300 kN<br />

Insgesamt 1163 Stück HLV®-Pfähle davon:<br />

• 189 Stück HLV®-Pfähle 118 bis 200 mm mantelverpresst<br />

als Tiefgründung eines Anlagenfundamentes mit Druck<br />

lasten bis 400 kN und Zuglasten bis 100 kN pro Pfahl<br />

• 46 Stück HLV®-Pfähle 118 bis 200 mm mantelverpresst<br />

(Drucklast bis 305 kN pro Pfahl) sowie 6 Stück HLV®-Pfäh<br />

le 170 bis 250 mm mantelverpresst (Druckkraft bis 720 kN<br />

pro Pfahl) als Fundierung eines Bürogebäudes.<br />

• 24 Stück HLV®-Pfähle 170 bis 250 mm mantelverpresst<br />

im Bereich einer bestehenden Kaimauer als Fundierung<br />

für eine Halle mit Drucklasten von 750 kN und Zuglasten<br />

von 200 kN pro Pfahl<br />

• 898 Stück HLV®-Pfähle 118 bis 200 mm mantelverpresst<br />

als Gründungspfähle und zur Auftriebssicherung mit<br />

Drucklasten von 200 kN und Zuglasten von 150 kN pro<br />

Pfahl


SLC STEEL LOGISTICS CENTER, LOBAU/VIENNA<br />

SLC Stahl Logistik Center GmbH is building a new steel processing<br />

plant at the Vienna oil terminal in Lobau. This location was<br />

chosen since the plant must be accessible by ship and rail.<br />

Due to the bombardment of the oil terminal during World<br />

War II and its subsequent use as an oil transshipment site, a<br />

contamination of the subsoil could not be precluded. Had the<br />

foundation been provided with bored piles, the proper disposal<br />

of the soil would have involved significant costs. The experts at<br />

Grund- Pfahl- und Sonderbau (GPS) found an alternative using<br />

driven piles.<br />

A total of 205 driven cast-in-situ piles using the Zeissl/GPS<br />

system were placed as a depth foundation for the three-aisled<br />

plant, consisting of a production, oil and metal warehouse. They<br />

will serve to bear the building load. Since an OMV medium-pressure<br />

gas line runs in close proximity to the three groups of piles,<br />

vibration tests to the line were conducted while the piles were<br />

being driven but the oscillations did not have a negative impact.<br />

The ground slab payload was dissipated into the ground via 898<br />

skin-grouted HLV® piles (118 mm). They also secure the plant<br />

against uplift. The building load was transferred into the ground<br />

by grouted HLV® piles (170 mm) at the harbor basin wall<br />

consisting of rear-anchored sheet pile. They had to be precisely<br />

inserted between the existing rear-anchorage. This was not a<br />

problem for the HLV® pile system used.<br />

Client SLC Stahl Logistik Center GmbH, Vienna<br />

Principal HABAU GmbH<br />

<strong>Special</strong> foundation contractor GPS Grund- Pfahl- und Sonderbau GmbH, Himberg<br />

Contact office@gps-bau.com<br />

Construction period October 2007 to April 2008<br />

Contract value EUR 0.94 million<br />

The following special foundation services were provided:<br />

DRIVEN PILES<br />

• 205 driven cast-in-situ piles, Zeissl/GPS system, with a load<br />

of up to 1300 kN<br />

A total of 1163 HLV® piles, including:<br />

• 189 HLV® piles (118 to 200 mm), grouted as deep<br />

foundation for the plant foundation to withstand a pressure<br />

load of up to 400 kN and a tensile load of up to 100 kN per<br />

pile<br />

• 46 HLV® piles (118 to 200 mm), grouted (pressure load<br />

of up to 305 kN per pile) and 6 HLV® piles (170 to 250 mm),<br />

shaft-grouted (pressure force of up to 720 kN per pile) as the<br />

foundation for an office building.<br />

• 24 HLV® piles (170 to 250 mm), grouted at an existing<br />

harbor wall as the foundation for a warehouse to withstand<br />

a pressure load of up to 750 kN and a tensile load of up to<br />

200 kN per pile.<br />

• 898 HLV® piles (118 to 200 mm), grouted as foundation<br />

piles and uplift control to withstand a pressure<br />

load of up to 200 kN and a tensile load of up to<br />

150 kN per pile<br />

27


RAMMPFAHLARBEITEN<br />

ZENTRALES AUSLIEFERUNGSLAGER HOFER IN LJUBLJANA<br />

Ab Mitte 2007 errichtete die Hofer KG ihr zentrales Aus-<br />

lieferungslager für Slowenien in der Nähe von Ljubljana. Von Mai<br />

bis September waren die Fundierungsarbeiten durchzuführen.<br />

Zur Lastableitung unter den hochbelasteten Köcherfundamenten<br />

wurden von der Grund- Pfahl und Sonderbau (GPS) mantelverpresste<br />

HLV®- Pfähle 170 bis 250 mm vorgeschlagen. Zur Verifizierung<br />

der angenommenen Pfahllasten wurden die Ergebnisse<br />

von insgesamt 15 Stk. Pfahllastversuchen ausgewertet, wobei<br />

Prüflasten bis zu max. 1.500 kN erreicht werden konnten.<br />

28<br />

Bauherr Hofer Nepremičnine d.o.o., Lukovica<br />

Ausführung <strong>Spezialtiefbau</strong> GPS Grund- Pfahl- und Sonderbau GmbH, Himberg<br />

Kontakt office@gps-bau.com<br />

Bauzeit Mai bis September 2007<br />

Auftragssumme <strong>Spezialtiefbau</strong> 1,7 Mio. EUR<br />

Nach Auswertung dieser Ergebnisse kamen in Summe 25.200 m<br />

HLV®-Pfähle d 170 bis 250 mm zur Ausführung. Drei parallel arbeitende<br />

Pfahlgeräteeinheiten ermöglichten eine termingerechte<br />

Fertigstellung der Arbeiten.<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• 25.200 m HLV®-Pfähle d 170 bis 250 mm mantelverpresst<br />

• 15 Stk. Pfahlprobebelastungen


CENTRAL HOFER DISTRIBUTION CENTER IN LJUBLJANA<br />

Hofer KG set up its central distribution center for Slovenia near<br />

Ljubljana in mid-2007. The special foundation work was executed<br />

from May to September.<br />

Grund- Pfahl und Sonderbau (GPS) suggested to use 170 to<br />

250 mm grouted HLV® piles to transfer the load under the<br />

highly burdened sleeve foundations. To verify the assumed pile<br />

loads, the results of 15 pile load tests were analyzed, achieving<br />

trial loads up to a max. of 1,500 kN.<br />

Client Hofer Nepremičnine d.o.o., Lukovica<br />

<strong>Special</strong> foundation contractor GPS Grund- Pfahl- und Sonderbau GmbH, Himberg<br />

Contact office@gps-bau.com<br />

Construction period May to September 2007<br />

Contract value EUR 1.7 million<br />

Upon analyzing the results, a total of 25,200 m HLV® d 170 to<br />

250 mm piles were driven. Three pile driving units worked simultaneously<br />

to make sure the work was completed on time.<br />

The following special foundation services were provided:<br />

• 25,200 m HLV® piles, d 170 to 250 mm, grouted<br />

• 15 pile load tests<br />

DRIVEN PILES<br />

29


RAMMPFAHLARBEITEN<br />

NÖ LANDESGARTENSCHAU TULLN<br />

RAMMPFAHLARBEITEN AM BAUMWIPFELWEG<br />

Eingebettet im Auwald nahe dem Stadtzentrum von Tulln entstand<br />

die Niederösterreichische Landesgartenschau 2008 „Garten<br />

Tulln“. Das Gelände ist insgesamt 50 ha groß. Auf 10 ha<br />

sind 42 Muster- und Schaugärten zu sehen, die dem neuesten<br />

Stand der Gartenkunst und den Anforderungen der natürlichen<br />

Gartenpflege entsprechen.<br />

Als besondere Attraktion erwartet den Besucher der Baumwipfelweg,<br />

der einen aufregenden Ausblick über die Baumkronen<br />

der Tullner Donaulandschaft und die Gärten ermöglicht. Bei diesem<br />

Bauwerk handelt es sich um eine hohe, schlanke Stahlkonstruktion,<br />

die aus mehreren Türmen mit übereinanderliegenden<br />

Plattformen besteht. Die maximale Höhe beträgt 30 m. Bedingt<br />

durch die Bodenverhältnisse und die Einleitung von Zug- und<br />

Horizontalkräften in den Boden wurde eine Zeissl-GPS Fundierung<br />

gewählt.<br />

30<br />

Bauherr NÖ Landesgartenschau Planungs- und Errichtungs- G.m.b.H.<br />

Ausführung <strong>Spezialtiefbau</strong> GPS Grund- Pfahl- und Sonderbau GmbH, Himberg<br />

Kontakt office@gps-bau.com<br />

Bauzeit Mai bis Juni 2007<br />

Auftragssumme <strong>Spezialtiefbau</strong> 0,15 Mio. EUR<br />

Beim Rammen der Pfähle musste auf die statisch erforderlichen<br />

Bewehrungen und die bestmögliche Schonung des alten Baum-<br />

und Wurzelbestandes große Rücksicht genommen werden.<br />

Die vorgeschriebene äußere Standsicherheit wurde durch das<br />

Rammkriterium bei der Herstellung nachgewiesen.<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• Fundierung: 28 Stk. Zeissl-GPS Pfähle d 50 cm<br />

• Pfahlkräfte:<br />

Minimum Zug - 720 kN<br />

Maximum Druck + 1.100 kN


LOWER AUSTRIAN STATE GARDEN SHOW IN TULLN<br />

DRIVEN PILE CONSTRUCTION AT BAUMWIPFELWEG<br />

„The Tulln Gardens,“ the 2008 Lower Austrian State Garden<br />

Show, is nestled in the alluvial forest near the center of Tulln.<br />

The grounds spread over 50 hectares of land. A total of 42 model<br />

and exhibition gardens on 10 hectares present the state of<br />

the art in landscaping according to ecological standards.<br />

Visitors can look forward to a special attraction at Baumwipfelweg,<br />

offering a breathtaking view over the treetops to Tulln‘s<br />

Danube landscape and the gardens. The tall, slim steel structure<br />

consists of several towers with projecting platforms. The maximum<br />

height is 30 m. A Zeissl-GPS foundation was selected due<br />

to the soil conditions and the transfer of tensile and horizontal<br />

forces into the soil.<br />

Maximum attention had to be paid to the static reinforcement<br />

requirements and the best possible protection of the old tree<br />

and root populations while the piles were being driven.<br />

DRIVEN PILES<br />

The required external stability was achieved by the driving criterion<br />

during construction.<br />

The following special foundation services were provided:<br />

• <strong>Foundation</strong>: 28 driven piles, Zeissl-GPS d 50 cm<br />

• Pile forces:<br />

Minimum Tension - 720 kN<br />

Maximum Pressure + 1100 kN<br />

Client NÖ Landesgartenschau Planungs- und Errichtungs- G.m.b.H.<br />

<strong>Special</strong> foundation contractor GPS Grund- Pfahl- und Sonderbau GmbH, Himberg<br />

Contact office@gps-bau.com<br />

Construction period May to June 2007<br />

Contract value EUR 0.15 million<br />

31


ERKUNDUNGSARBEITEN<br />

KRAFTWERK KüHTAI / TIROL<br />

Die Kraftwerksgruppe Sellrain-Silz soll zu den bestehenden Speichern<br />

Längental und Finstertal einen Jahresspeicher Kühtai mit<br />

ca. 30 Mio. m³ im hinteren Längental bekommen.<br />

Für die geologisch-geotechnische Erkundung wurden von der<br />

Grund- Pfahl- und Sonderbau (GPS) Rotationsbohrungen mit<br />

durchgehendem Kerngewinn durchgeführt. Zu den Bohrpunkten<br />

auf mehr als 2.000 m Höhe war für die Gerätschaft keine Zufahrt<br />

vorhanden. Das Gelände ist so steil, dass aufwändige und<br />

sichere Holz-Bohrplattformen konstruiert werden mussten.<br />

Diese Plattformen wurden nach Fertigstellung der Bohrungen<br />

abgetragen und der ursprüngliche Zustand der Geländeform<br />

wieder hergestellt.<br />

Bohrgerät, Zubehör und eine Unterkunft wurden mit dem Hubschrauber<br />

auf die einzelnen Bohransatzpunkte transportiert.<br />

Trotz widriger Wetterbedingungen wurden neun Bohrungen bis<br />

zu einer Endtiefe von 200 m vorgenommen.<br />

32<br />

Bauherr TIWAG - Tiroler Wasserkraft AG<br />

Ausführung <strong>Spezialtiefbau</strong> Grund- Pfahl- und Sonderbau GmbH, Himberg<br />

Kontakt office@gps-bau.com<br />

Bauzeit August bis Oktober 2007<br />

Auftragssumme <strong>Spezialtiefbau</strong> 1,4 Mio. EUR<br />

Vier davon waren bis zu 45 Grad schräg. In allen wurden geophysikalische<br />

und geomechanische Versuche zur Feststellung des<br />

Gebirgsaufbaus durchgeführt.<br />

Zusätzlich wurden in zwei Bohrungen Inklinometer eingebaut,<br />

die restlichen wurden als Bergwassermess-Stellen ausgebaut.<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• 9 Stk. Kernbohrungen mit einer Endtiefe bis zu 200 m<br />

4 davon geneigt bis zu einer maximalen Neigung von 45°<br />

• Ausbau der Kernbohrungen mit Inklinometer und<br />

Bergwassermess-Stellen<br />

• Geophysikalische und geomechanische Versuche in allen<br />

Bohrungen


KüHTAI POWER PLANT / TyROL<br />

The Kühtai annual reservoir with approx. 30 million m³ in the<br />

rear Längental will be added to the Sellrain-Silz group of power<br />

plants to supplement the existing Längental and Finstertal<br />

reservoirs.<br />

Grund- Pfahl- und Sonderbau (GPS) carried out geologic-geotechnical<br />

explorations by means of rotational drilling with continuous<br />

core recovery. No access roads were available to bring the<br />

equipment to the drill points at an altitude of over 2000 m. The<br />

terrain was so steep that elaborate wooden drill platforms had<br />

to be built for safe transport.<br />

The platforms were removed after the drilling was completed<br />

and the area returned to its original condition.<br />

Drilling equipment, accessories and lodgings were transported to<br />

the individual drilling points by helicopter.<br />

Despite adverse weather conditions, nine bore holes were drilled<br />

to a depth of 200 m.<br />

Client TIWAG - Tiroler Wasserkraft AG<br />

<strong>Special</strong> foundation contractor GPS Grund- Pfahl- und Sonderbau GmbH, Himberg<br />

Contact office@gps-bau.com<br />

Construction period August to October 2007<br />

Contract value EUR 1.4 million<br />

GEOTECHNICAL INVESTIGATIONS<br />

Four of them were inclined up to 45 degrees. Geophysical and<br />

geometrical tests were performed in all of the holes to establish<br />

the rock composition.<br />

In addition, inclinometers were installed in two holes, the others<br />

were enlarged to serve as mountain water measuring stations.<br />

The following special foundation services were provided:<br />

• 9 rotary core drilling holes with a final depth of up to 200 m<br />

4 of which were inclined up to a maximum of 45°<br />

• Installing of inclinometers and water measuring devices into<br />

the bore holes<br />

• Geophysical and geomechanical tests in all holes<br />

33


VEREISUNGSARBEITEN<br />

CITy-TUNNEL LEIPZIG, VEREISUNGSARBEITEN<br />

Vereisungsarbeiten sind eine Spezialität der Experten der Stump<br />

<strong>Spezialtiefbau</strong> GmbH in Deutschland und Grund- Pfahl- und<br />

Sonderbau in Österreich. Vor kurzem wurden am Wiener U-Bahn<br />

Baulos U 2/1 äußerst anspruchsvolle Bohrarbeiten für die Herstellung<br />

der Vereisung unter dem Wiener Donaukanal vorgenommen.<br />

Vergleichbar war die Aufgabe am Baulos B des Jahrhundertprojektes<br />

„City Tunnel Leipzig“.<br />

Der Lückenschluss erfolgte vorab mit Düsenstrahlkörpern. Das<br />

erfüllte jedoch nur statisch konstruktive Anforderungen. Um die<br />

erforderliche Dichtheit zu gewährleisten, wurde entlang der DSV<br />

Lückenschlüsse mit Vereisungslanzen ein Dichtkörper erzeugt.<br />

Aufgeteilt auf jeweils zwei Höhenstaffeln sind dafür aus dem<br />

34<br />

Bauherr DB Energie GmbH, DB Netz AG, DB Station & Service AG,<br />

vertreten durch den Freistaat Sachsen, endvertreten durch DEGES<br />

(Deutsche Einheit Fernstraßenplanungs- und – Bau GmbH).<br />

Auftraggeber ARGE City Tunnel Leipzig Los B<br />

Dywidag Bau GmbH, ALPINE Bau Deutschland AG, Oevermann GmbH & Co.KG,<br />

Universale Grund- und Sonderbau GmbH Berlin<br />

Ausführung <strong>Spezialtiefbau</strong> Stump <strong>Spezialtiefbau</strong> GmbH, Niederlassung Berlin<br />

Kontakt info@stump.de<br />

Bauzeit 2005 bis 2007<br />

Auftragssumme <strong>Spezialtiefbau</strong> ca. 1,4 Mio. EUR<br />

Tunnel heraus 28 Vereisungslanzen und sechs Temperaturmesslanzen<br />

bis auf eine Tiefe von ca. 23 m eingebaut worden. Um ein<br />

wirtschaftlich, und auch technisch optimales Ergebnis zu erzielen,<br />

wurde ein eigenes Steuerungs- und überwachungssystem angewendet.<br />

Mit automatischen Mengenmess-Sensoren, Sensoren im<br />

Vereisungskörper und in den Lanzen und mehrfach abgesicherten<br />

Alarmierungseinrichtungen konnte der Gefrierungsprozess<br />

vollelektronisch überwacht und ferngesteuert werden.<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• 28 Stk. Vereisungslanzen<br />

• 320 m³ Vereisungskörper


LEIPZIG CITy TUNNEL, GROUND FREEZING<br />

Ground freezing is a specialised technique used by the experts at<br />

Stump <strong>Spezialtiefbau</strong> GmbH in Germany and Grund- Pfahl- und<br />

Sonderbau in Austria. Highly sophisticated drilling was recently<br />

required for freezing operations under Vienna‘s Danube Channel<br />

at the Vienna Subway contract section U 2/1.<br />

Contract section B of the centennial „Leipzig City Tunnel“ project<br />

was a comparable project. Gaps were temporarily closed with<br />

grouted bodies, although they only met the static design requirements.<br />

To ensure impermeability, a freeze wall was formed with<br />

freeze lances to close the gaps in the jet grouted body. 28 freeze<br />

lances and six temperature measurement lances were installed in<br />

GROUND FREEZING<br />

Client DB Energie GmbH, DB Netz AG, DB Station & Service AG, represented by the State of<br />

Saxony, in turn represented by DEGES<br />

(Deutsche Einheit Fernstrassenplanungs- und – Bau GmbH).<br />

Principal Leipzig City Tunnel Leipzig Contract Section B JV<br />

Dywidag Bau GmbH, ALPINE Bau Deutschland AG, Oevermann GmbH & Co.KG,<br />

Universale Grund- und Sonderbau GmbH, Berlin<br />

<strong>Special</strong> foundation contractor Stump <strong>Spezialtiefbau</strong> GmbH, Berlin Branch<br />

Contact info@stump.de<br />

Construction period 2005 to 2007<br />

Contract value approx. EUR 1.4 million<br />

the tunnel to a depth of approx. 23 m at two graduated heights.<br />

An automatic control and monitoring system was used for maximum<br />

economical and technical results. Automatic mass measuring<br />

sensors, sensors in the freezing body and in the lances as<br />

well as backed-up alarm equipment allowed the freezing process<br />

to be electronically monitored and remote controlled.<br />

The following special foundation services were provided:<br />

• 28 freeze lances<br />

• 320 m³ freeze wall<br />

35


FELSSICHERUNG<br />

B180 RESCHENSTRASSE TIROL, ERRICHTUNG VON SEILSPERREN<br />

Die Niederlassung Tirol der GPS Grund- Pfahl- und Sonderbau<br />

GmbH ist spezialisiert auf Arbeiten in hochalpinem Gelände.<br />

Dazu gehören Seilsperren, Hangsicherungen, Lawinenverbauten<br />

und Felsräumarbeiten.<br />

Zur Sicherung der B180 Landesstraße in Tirol wurden 250 m Seilsperren<br />

mit einer Energieaufnahme von 2.000 kJ und einer Höhe<br />

von max. 5 m in unmittelbarem Bereich der Straße unterhalb einer<br />

ca. 500 m hohen Felswand hergestellt. Erschwert wurden die<br />

Arbeiten durch die extremen Geländeverhältnisse mit Hangneigungen<br />

von 30° bis 50° und das bei Temperaturen bis zu -20°C.<br />

36<br />

Bauherr Land Tirol<br />

Ausführung <strong>Spezialtiefbau</strong> GPS Grund- Pfahl- und Sonderbau GmbH, Niederlassung Tirol<br />

Kontakt office@gps-bau.com<br />

Bauzeit November 2006 bis Februar 2007<br />

Auftragssumme <strong>Spezialtiefbau</strong> ca. 0,2 Mio. EUR<br />

Folgende <strong>Spezialtiefbau</strong>maßnahmen wurden realisiert:<br />

• 30 m Seilsperren 1.000 kJ, Nutzhöhe 4,0 m<br />

• 220 m Seilsperre 2.000 kJ, Nutzhöhe 5,0 m


The Tyrolean Branch of GPS Grund- Pfahl- und Sonderbau GmbH<br />

is specialized in working in high alpine terrain. Its services include<br />

the installation of rope barriers, slope stabilization, avalanche<br />

protectors and rock clearing.<br />

250 m of rope barriers with an energy absorption of 2000 kJ<br />

and a height of max. 5 m were installed directly next to the road<br />

beneath a 500 m rock wall to ensure the safety of the B180 state<br />

highway in Tyrol. The work was impeded by the extreme terrain<br />

with inclinations ranging from 30° to 50° at temperatures down<br />

to -20°C.<br />

Client State of Tyrol<br />

<strong>Special</strong> foundation contractor GPS Grund- Pfahl- und Sonderbau GmbH, Tyrol Branch<br />

Contact office@gps-bau.com<br />

Construction period November 2006 to February 2007<br />

Contract value approx. EUR 0.2 million<br />

ROCK STABILISATION<br />

B180 RESCHENSTRASSE, TyROL ROPE BARRIER INSTALLATION<br />

The following special foundation services were provided:<br />

• 30 m rope barriers 1000 kJ, height 4.0 m<br />

• 220 m rope barriers 2000 kJ, height 5.0 m<br />

37


STANDORT<br />

STANDORTE<br />

38<br />

Grund-, Pfahl- und Sonderbau GmbH<br />

Universale Grund- und Sonderbau GmbH<br />

Stump <strong>Spezialtiefbau</strong> GmbH<br />

/ LOCATIONS<br />

Hannover<br />

Langenfeld<br />

Dornbirn<br />

Hamburg<br />

Colbitz<br />

München<br />

Berlin<br />

Prag<br />

Kematen<br />

Chemnitz<br />

Poznań<br />

Klagenfurt<br />

Brno<br />

Warschau<br />

Himberg bei Wien<br />

Krakau


Medieninhaber und Herausgeber:<br />

Grund- Pfahl- und Sonderbau GmbH<br />

Industriestraße 27a<br />

A-2325 Himberg<br />

Tel. +43 2235 87 777-0<br />

Fax +43 2235 86 561<br />

E-mail: office@gps-bau.com<br />

www.gps-bau.com<br />

Redaktion, Gestaltung und Produktion:<br />

Grund- Pfahl- und Sonderbau GmbH<br />

1. Ausgabe, September 2008<br />

Hersteller:<br />

Alwa und Deil Druckerei GmbH, Wien<br />

IMPRESSUM


ÖSTERREICH / AUSTRIA<br />

Grund- Pfahl- und Sonderbau GmbH<br />

Hauptverwaltung<br />

Industriestraße 27a<br />

2325 Himberg bei Wien<br />

Österreich<br />

Tel. +43 2235 87777-0<br />

Fax +43 2235 86561<br />

www.gps-bau.com<br />

office@gps-bau.com<br />

Grund- Pfahl- und Sonderbau GmbH<br />

Filiale GPS Kärnten<br />

Josef-Sablatnig-Straße 251<br />

9020 Klagenfurt<br />

Tel. +43 463 33533-0<br />

Fax +43 463 33533-709<br />

Grund- Pfahl- und Sonderbau GmbH<br />

Filiale GPS Kematen<br />

Messerschmittweg 13<br />

6175 Kematen<br />

Tel. +43 5232 3333-122<br />

Fax +43 5232 2617<br />

Grund- Pfahl- und Sonderbau GmbH<br />

Filiale GPS Dornbirn<br />

Lustenauerstraße 56<br />

6850 Dornbirn<br />

Tel. +43 5572 398855<br />

Fax +43 5572 386279<br />

DEUTSCHLAND / GERMANY<br />

Universale Grund- und Sonderbau GmbH<br />

Hauptverwaltung<br />

Kurfürstendamm 38/39<br />

D-10719 Berlin<br />

Tel. +49 30 53006-0<br />

Fax +49 30 5354637<br />

www.universale-gsb.de<br />

gsb.berlin@gps-bau.com<br />

Universale Grund- und Sonderbau GmbH<br />

Zweigniederlassung Hamburg<br />

Ludwig-Erhard-Straße 37<br />

D-20459 Hamburg<br />

Tel. +49 40 3197476-51<br />

Fax +49 40 3197476-52<br />

Universale Grund- und Sonderbau GmbH<br />

Zweigniederlassung München<br />

Am Lenzenfleck 1-3<br />

85737 Ismaning<br />

Tel. +49 89 960 701-40<br />

Fax +49 89 960 701-42<br />

40<br />

Universale Grund- und Sonderbau GmbH<br />

Zweigniederlassung Langenfeld<br />

Friedrich-Krupp-Strasse 18<br />

40764 Langenfeld<br />

Tel. +49 2173 409 92-24<br />

Fax +49 2173 409 92-26<br />

Stump <strong>Spezialtiefbau</strong> GmbH<br />

Hauptverwaltung<br />

Am Lenzenfleck 1-3<br />

85737 Ismaning<br />

Tel. +49 89 960 701-0<br />

Fax +49 89 963 151<br />

www.stump.de<br />

info@stump.de<br />

Stump <strong>Spezialtiefbau</strong> GmbH<br />

Zweigniederlassung Berlin<br />

Kurfürstendamm 38/39<br />

10719 Berlin<br />

Tel. +49 30 754 904-0<br />

Fax +49 30 754 904-20<br />

Stump <strong>Spezialtiefbau</strong> GmbH<br />

Zweigniederlassung Chemnitz<br />

Blankenauer Straße 99<br />

09113 Chemnitz<br />

Tel. +49 371 262 519-0<br />

Fax +49 371 262 519-30<br />

Stump <strong>Spezialtiefbau</strong> GmbH<br />

Zweigniederlassung Hannover<br />

Eichenbrink 7<br />

30453 Hannover<br />

Tel. +49 511 94 999-0<br />

Fax +49 511 499 498<br />

Stump <strong>Spezialtiefbau</strong> GmbH<br />

Zweigniederlassung Langenfeld<br />

Friedrich-Krupp Straße 18<br />

40764 Langenfeld<br />

Tel. +49 2173 27 197-0<br />

Fax +49 2173 27 197-990<br />

Stump <strong>Spezialtiefbau</strong> GmbH<br />

Zweigniederlassung München<br />

Am Lenzenfleck 1-3<br />

85737 Ismaning<br />

Tel. +49 89 960 701-0<br />

Fax +49 89 963 151<br />

Stump <strong>Spezialtiefbau</strong> GmbH<br />

Geschäftsstelle Colbitz<br />

Südstraße 2<br />

39326 Colbitz<br />

Tel. +49 39207 856-0<br />

Fax +49 39207 856-50<br />

POLEN / POLAND<br />

Stump - Hydrobudowa Sp. z o.o.<br />

ul. 29 Listopada 10<br />

00-465 Warszawa<br />

Tel. +48 22 5596 040<br />

Fax +48 22 5596 041<br />

www.stump-hydrobudowa.pl<br />

warszawa@stump-hydrobudowa.pl<br />

Stump - Hydrobudowa Sp. z o.o.<br />

ul. Bociana 6<br />

31-231 Kraków<br />

Tel. +48 12 61 641-91<br />

Fax +48 12 61 641-92<br />

Stump - Hydrobudowa Sp. z o.o.<br />

ul. Dšbrowskiego 75/50<br />

60-523 Poznań<br />

Tel. +48 61 82 661-51<br />

Fax +48 61 82 062-84<br />

TSCHECHIEN / CZECH REPUBLIC<br />

STUMP <strong>Spezialtiefbau</strong> spol.s r.o.<br />

Úvalská 28<br />

100 00 Praha 10<br />

Czech republic<br />

Tel. +42 274 781 537<br />

+42 274 781 538<br />

Fax +42 274 781 516<br />

www.stump.cz<br />

info@stump.cz<br />

STUMP <strong>Spezialtiefbau</strong> spol.s r.o.<br />

Závod GEOSPOL Brno<br />

Jahodová 523/58 620 00<br />

620 00 Brno - Brněnské Ivanovice<br />

Tel. +420 545 558 000<br />

Fax +420 545 558 023

Hurra! Ihre Datei wurde hochgeladen und ist bereit für die Veröffentlichung.

Erfolgreich gespeichert!

Leider ist etwas schief gelaufen!